Share Sandy Creek tanks: Kalperri Road on FacebookShare Sandy Creek tanks: Kalperri Road on TwitterShare Sandy Creek tanks: Kalperri Road on LinkedinEmail Sandy Creek tanks: Kalperri Road link
Water infrastructure works at Sandy Creek
Construction is now underway on two new 10 million litre above-ground water storage tanks, a new control valve building, and an underground trunk main connecting the tanks to the existing Barossa Trunk Main.
These upgrades will enhance network resilience, improve operability, and ensure reliable water services for current and future customers in the area.
For details about electrical connection to the tanks site, visit SA Power Networks.
Where we’re working (See map below for details)
The storage tanks are being built on secured land on the eastern side of Kalperri Road, approximately halfway between the Barossa Valley Highway and Balmoral Road in Sandy Creek.
Water mains pipes are being installed from the tank site to the railway line near Barossa Valley Way within the land east of Kalperri Road. Pipes will then cross under Kalperri Road and continue on private land through to Kalbeeba Road.
Pipes are also being laid from the southern side of the tanks along the paddock boundary, continuing north to the end of Warner Court.
What to expect
Changed traffic arrangements will be in place across the area until 2026
You may notice some noise, vibration and dust during construction
We’ll continue working closely with the community to minimise impacts wherever possible
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Construction is now underway on two new 10 million litre above-ground water storage tanks, a new control valve building, and an underground trunk main connecting the tanks to the existing Barossa Trunk Main.
These upgrades will enhance network resilience, improve operability, and ensure reliable water services for current and future customers in the area.
For details about electrical connection to the tanks site, visit SA Power Networks.
Where we’re working (See map below for details)
The storage tanks are being built on secured land on the eastern side of Kalperri Road, approximately halfway between the Barossa Valley Highway and Balmoral Road in Sandy Creek.
Water mains pipes are being installed from the tank site to the railway line near Barossa Valley Way within the land east of Kalperri Road. Pipes will then cross under Kalperri Road and continue on private land through to Kalbeeba Road.
Pipes are also being laid from the southern side of the tanks along the paddock boundary, continuing north to the end of Warner Court.
What to expect
Changed traffic arrangements will be in place across the area until 2026
You may notice some noise, vibration and dust during construction
We’ll continue working closely with the community to minimise impacts wherever possible
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Share Works commencing – Kalperri Road to Kalbeeba Road on FacebookShare Works commencing – Kalperri Road to Kalbeeba Road on TwitterShare Works commencing – Kalperri Road to Kalbeeba Road on LinkedinEmail Works commencing – Kalperri Road to Kalbeeba Road link
When: 7 April to December 2026
Where: Between Kalperri Road and Kalbeeba Road, Sandy Creek
Hours of work: Monday to Saturday, 7.00am – 5.00pm (with some night works as required)
Key details:
crews will be installing a new 1.2km water main alongside the existing network to increase capacity and reliability
works will take place on private land between Kalperri Road and Kalbeeba Road
construction activities will include excavators, cranes and truck movements to and from site
arborist works are scheduled for mid-April to support pipe installation
you may notice noise, dust and general construction activity during these works
speed restrictions will remain in place on Kalperri Road, with any traffic changes communicated in advance
access to properties will be maintained, and advance notice will be provided if water supply is temporarily impacted.
These works form part of SA Water’s broader infrastructure upgrades to support growth and maintain reliable services across the region.
We appreciate your patience while we complete these important works.
When: 7 April to December 2026
Where: Between Kalperri Road and Kalbeeba Road, Sandy Creek
Hours of work: Monday to Saturday, 7.00am – 5.00pm (with some night works as required)
Key details:
crews will be installing a new 1.2km water main alongside the existing network to increase capacity and reliability
works will take place on private land between Kalperri Road and Kalbeeba Road
construction activities will include excavators, cranes and truck movements to and from site
arborist works are scheduled for mid-April to support pipe installation
you may notice noise, dust and general construction activity during these works
speed restrictions will remain in place on Kalperri Road, with any traffic changes communicated in advance
access to properties will be maintained, and advance notice will be provided if water supply is temporarily impacted.
These works form part of SA Water’s broader infrastructure upgrades to support growth and maintain reliable services across the region.
We appreciate your patience while we complete these important works.
Share Construction works update – change in work hours on FacebookShare Construction works update – change in work hours on TwitterShare Construction works update – change in work hours on LinkedinEmail Construction works update – change in work hours link
Kalperri Road Tank Site, Sandy Creek
Tank construction works will continue through to late 2026.
To maintain the project schedule we will commence onsite works from 6.00am on Monday to Saturdays.
What:Works will commence from 6.00amon Mondays to Saturdays, the usual end time of 5.00pm will continue during this period
When: Monday 5 January 2026 to Saturday, 30 May 2026
Why: Commencing works earlier is to:
maximises productivity and safety by undertaking works during the most stable weather conditions earlier in the day
eliminates the need for temporary lighting, with works commencing at sunrise
aligns with wide-load transport curfews and early deliveries
reduces noise to neighbouring residents and the local community (due to working in less windy conditions)
reduces the risk of program delays caused by heat restrictions and afternoon wind which impacts elevated work activities
If there are changes to these times, we will provide advance notification.
What to expect:
Truck activity will continue, crews will be on site
Access to properties on Kalperri Road will be maintained
There will be some noise and dust suppression activities will be in place.
Please note:Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
Share Stay informed and have your say on FacebookShare Stay informed and have your say on TwitterShare Stay informed and have your say on LinkedinEmail Stay informed and have your say link
As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.
Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.
As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.
Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.