Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads
Share Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads on FacebookShare Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads on TwitterShare Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads on LinkedinEmail Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads link
From April 2025, construction will begin to install approximately 7.5 kilometres of new wastewater mains in Reid, Willaston, Gawler Belt, and Roseworthy, along with a new pump station on Davidson Road in Reid. This new infrastructure will provide reliable services for existing customers and support future growth in the Roseworthy area.
Where works will occur (see map below for details) :
Reid: Paternoster Road
Willaston: Kentish Road
Gawler Belt: Kentish and Redbanks Roads
Roseworthy: Redbanks and Twartz Roads
What to expect
We acknowledge that some people may be affected by these works. Those impacted will be notified in advance. We will also work closely with potentially impacted property owners, residents, businesses and road users before and during works.
We’re exploring all options to quickly complete this important work while minimising traffic interruptions, road closures and detours. These include scheduling day, night and weekend works, as needed, as well as refining the pipe alignment, where possible.
Nearby Works As part of this major upgrade, other nearby works are also happening on:
From April 2025, construction will begin to install approximately 7.5 kilometres of new wastewater mains in Reid, Willaston, Gawler Belt, and Roseworthy, along with a new pump station on Davidson Road in Reid. This new infrastructure will provide reliable services for existing customers and support future growth in the Roseworthy area.
Where works will occur (see map below for details) :
Reid: Paternoster Road
Willaston: Kentish Road
Gawler Belt: Kentish and Redbanks Roads
Roseworthy: Redbanks and Twartz Roads
What to expect
We acknowledge that some people may be affected by these works. Those impacted will be notified in advance. We will also work closely with potentially impacted property owners, residents, businesses and road users before and during works.
We’re exploring all options to quickly complete this important work while minimising traffic interruptions, road closures and detours. These include scheduling day, night and weekend works, as needed, as well as refining the pipe alignment, where possible.
Nearby Works As part of this major upgrade, other nearby works are also happening on:
Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads is currently at this stage
Work to establish our compound will commence from March. Mobilisation and compound establishment at three locations (Pump station on Davidson Road site at Reid plus Twartz Road, and Kentish Roads.
April 2025: Pipeline installation begins from Twartz Road, Roseworthy
this is an upcoming stage for Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads
Pipe-laying work begins at Twartz Road and progresses toward Kentish Road and Paternoster Road throughout 2025. Multiple crews will be involved in this work. Reinstatement will begin once the new pipeline has been tested.
Mid 2025: Pump Station work
this is an upcoming stage for Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads
Pump station work is expected to commence on Davidson Road
Pipe commissioning and roads, footpaths and vegetation reinstatement
this is an upcoming stage for Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads
Reinstatement begins once the new pipeline has been commissioned.
Mid 2026: Completion of major works
this is an upcoming stage for Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads
Major construction works are expected to continue until the middle of 2026.