Share Upcoming day and night works near Warner Ct and Kalperri Rd/Barossa Valley Way intersection, Sandy Creek on Facebook
Share Upcoming day and night works near Warner Ct and Kalperri Rd/Barossa Valley Way intersection, Sandy Creek on Linkedin
Email Upcoming day and night works near Warner Ct and Kalperri Rd/Barossa Valley Way intersection, Sandy Creek link
We’re upgrading essential water infrastructure in Sandy Creek. Ahead of installing new pipes to our new tanks site off Kalperri Road, we’ll be making critical connections to the existing network, over two 36-hour periods.
When:
- 7am Thursday 18 September – 7pm Friday 19 September 2025
- 7am Thursday 25 September – 7am Saturday 27 September 2025
Where:
Works will occur in two locations within our easement as shown below:
Near Kalperri Rd and Barossa Valley Way and near Warner Ct (western end)

Key details:
- to prepare for these new connections, you may notice controlled discharge of dechlorinated potable water from the pipe near these locations.
- Crews will be on-site using cutting and welding equipment, a crane, light towers, excavators, trucks and other machinery.
- Site access will be via our easement within the paddock and via Warner Court.
-
Noise and light are expected, including noticeable activity during night works.
- Please avoid on-street parking at the western end of Warner Court during work times.
- If your water supply is temporarily impacted, we’ll notify you in advance.
Please note: Timeline dates are subject to change based on program requirements and weather conditions
We appreciate your patience as we complete this important work.
Find out about detours near you
Read more about how we restore any roads, footpaths or the environment impacted by our works.
Share Works commencing near Warner Court, Sandy Creek on Facebook
Share Works commencing near Warner Court, Sandy Creek on Linkedin
Email Works commencing near Warner Court, Sandy Creek link
We’re upgrading essential water infrastructure near Warner Court. Ahead of new pipes being installed to our new tanks site off Kalperri Road, we will be undertaking preparation work to connect to existing infrastructure.
When: Friday 22 August 2025 to late September 2025
Hours of work: 7.00 am - 5.00 pm, Monday to Friday (with some Saturday works if required)
Key details:
- There will be crews on-site using equipment such as a crane, rollers, excavators and trucks, along with some tree removal and surveying activities.
- Access to our site will be via our easement in the neighbouring paddock and Warner Court.
- Please avoid on-street parking at the western end of Warner Court during work times.
- Some noise is expected while works are underway.
- If your water supply is temporarily impacted, we’ll notify you in advance.
- Further works are planned for late September and we’ll provide an update before they begin.
Work area: Works will be undertaken in our easement as shown in the map below. 
Please note: Timeline dates are subject to change based on program requirements and weather conditions. We appreciate your patience as we complete this important work.
Go back to the project home page
Share Stay informed and have your say on Facebook
Share Stay informed and have your say on Linkedin
Email Stay informed and have your say link
As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.
Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.
Share Project Commencement on Facebook
Share Project Commencement on Linkedin
Email Project Commencement link
When: Late March 2025 until 2026
Hours of work: 7:00 am – 5:00 pm, Monday to Friday with some weekends as required
Key details:
- earthwork starting in late March followed by the construction of tanks and instillation of pipes
- during works, traffic management may be in place adjacent to the work locations
- local access will be maintained
- expect some noise, dust and vibration
- We will manage works to minimise disturbances as much as possible.
Read more about how we restore any roads, footpaths or the environment impacted by our works.