Sandy Creek tanks: Kalperri Road

Share Sandy Creek tanks: Kalperri Road on Facebook Share Sandy Creek tanks: Kalperri Road on X (formerly Twitter) Share Sandy Creek tanks: Kalperri Road on Linkedin Email Sandy Creek tanks: Kalperri Road link

Water infrastructure works at Sandy Creek

Construction is now underway on two new 10 million litre above-ground water storage tanks, a new control valve building, and an underground trunk main connecting the tanks to the existing Barossa Trunk Main.

These upgrades will enhance network resilience, improve operability, and ensure reliable water services for current and future customers in the area.

For details about electrical connection to the tanks site, visit SA Power Networks.

Where we’re working
(See map below for details)

  • The storage tanks are being built on secured land on the eastern side of Kalperri Road, approximately halfway between the Barossa Valley Highway and Balmoral Road in Sandy Creek.
  • Water mains pipes are being installed from the tank site to the railway line near Barossa Valley Way within the land east of Kalperri Road. Pipes will then cross under Kalperri Road and continue on private land through to Kalbeeba Road.
  • Pipes are also being laid from the southern side of the tanks along the paddock boundary, continuing north to the end of Warner Court.

What to expect

  • Changed traffic arrangements will be in place across the area until 2026
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads

Gawler East: Martin Road, Concordia Road and Sunnydale Avenue

Need more information?

Visit our FAQs page for answers to the most asked questions.

Go back to the project home page

Water infrastructure works at Sandy Creek

Construction is now underway on two new 10 million litre above-ground water storage tanks, a new control valve building, and an underground trunk main connecting the tanks to the existing Barossa Trunk Main.

These upgrades will enhance network resilience, improve operability, and ensure reliable water services for current and future customers in the area.

For details about electrical connection to the tanks site, visit SA Power Networks.

Where we’re working
(See map below for details)

  • The storage tanks are being built on secured land on the eastern side of Kalperri Road, approximately halfway between the Barossa Valley Highway and Balmoral Road in Sandy Creek.
  • Water mains pipes are being installed from the tank site to the railway line near Barossa Valley Way within the land east of Kalperri Road. Pipes will then cross under Kalperri Road and continue on private land through to Kalbeeba Road.
  • Pipes are also being laid from the southern side of the tanks along the paddock boundary, continuing north to the end of Warner Court.

What to expect

  • Changed traffic arrangements will be in place across the area until 2026
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads

Gawler East: Martin Road, Concordia Road and Sunnydale Avenue

Need more information?

Visit our FAQs page for answers to the most asked questions.

Go back to the project home page

  • Temporary Road Closure – Kalperri Road

    Share Temporary Road Closure – Kalperri Road on Facebook Share Temporary Road Closure – Kalperri Road on X (formerly Twitter) Share Temporary Road Closure – Kalperri Road on Linkedin Email Temporary Road Closure – Kalperri Road link

    To facilitate the installation of a scour valve chamber, which will support the ongoing maintenance of the water network, Kalperri Road will be temporarily closed from Monday 29 June to Friday 3 July.

    When: Monday 29 June to Friday 3 July, 7:00 am – 5:00 pm

    Where: Kalperri Road, Kalbeeba

    Key details:

    • Kalperri Road will be closed next to the rail line from 7:00 am to 5:00 pm each day.
    • Local traffic will be maintained via Balmoral Road.
    • Traffic will be detoured via Kalbeeba Road and Williamstown Road. Please follow signage onsite.
    • We anticipate this will be the longest road closure required as part of these works. There may be one or two additional single-day closures over the coming month to complete the remaining activities.
    • We apologise for the inconvenience and thank you for your patience while these essential works are completed.

    To facilitate the installation of a scour valve chamber, which will support the ongoing maintenance of the water network, Kalperri Road will be temporarily closed from Monday 29 June to Friday 3 July.

    When: Monday 29 June to Friday 3 July, 7:00 am – 5:00 pm

    Where: Kalperri Road, Kalbeeba

    Key details:

    • Kalperri Road will be closed next to the rail line from 7:00 am to 5:00 pm each day.
    • Local traffic will be maintained via Balmoral Road.
    • Traffic will be detoured via Kalbeeba Road and Williamstown Road. Please follow signage onsite.
    • We anticipate this will be the longest road closure required as part of these works. There may be one or two additional single-day closures over the coming month to complete the remaining activities.
    • We apologise for the inconvenience and thank you for your patience while these essential works are completed.
  • Preparing to turn on tanks - various works

    Share Preparing to turn on tanks - various works on Facebook Share Preparing to turn on tanks - various works on X (formerly Twitter) Share Preparing to turn on tanks - various works on Linkedin Email Preparing to turn on tanks - various works link

    Between June through to October, we will be preparing to bring new tanks and supporting infrastructure at the Sandy Creek site online and connect to the existing network.

    What to expect

    • water being released into the Sandy Creek natural creek bed, entering via council swales off Kalperri Road and flowing through nearby properties
    • temporary fencing and equipment set up at various points around the site
    • some works will occur 24/7, including overnight
    • planned network outages with advance notice provided to impacted customers.

    Learn more about the commissioning process

    Between June through to October, we will be preparing to bring new tanks and supporting infrastructure at the Sandy Creek site online and connect to the existing network.

    What to expect

    • water being released into the Sandy Creek natural creek bed, entering via council swales off Kalperri Road and flowing through nearby properties
    • temporary fencing and equipment set up at various points around the site
    • some works will occur 24/7, including overnight
    • planned network outages with advance notice provided to impacted customers.

    Learn more about the commissioning process

  • Construction works update – temporary change in work hours

    Share Construction works update – temporary change in work hours on Facebook Share Construction works update – temporary change in work hours on X (formerly Twitter) Share Construction works update – temporary change in work hours on Linkedin Email Construction works update – temporary change in work hours link

    Kalperri Road Tank Site Sandy Creek

    Tank construction works will continue through to late 2026.

    To maintain the project schedule, we will be working some Sundays.

    What: Works will continue during standard construction hours of 6.00 am to 5.00 pm Monday to Saturday. Additional works will also be undertaken on Sundays between 7.00 am and 5.00 pm.

    When: Sunday 14 June 2026 – Sunday 5th July 2026

    Why: To maintain the project schedule and maximise available construction time and help offset weather-related disruptions experienced during recent weeks.

    What to expect:

    • Construction activities will occur on Sundays during the notified work hours.

    • Access to properties on Kalperri Road will be maintained.

    • Some noise associated with construction activities can be expected.

    • Existing speed restrictions will remain in place for the safety of road users and construction personnel.

    Kalperri Road Tank Site Sandy Creek

    Tank construction works will continue through to late 2026.

    To maintain the project schedule, we will be working some Sundays.

    What: Works will continue during standard construction hours of 6.00 am to 5.00 pm Monday to Saturday. Additional works will also be undertaken on Sundays between 7.00 am and 5.00 pm.

    When: Sunday 14 June 2026 – Sunday 5th July 2026

    Why: To maintain the project schedule and maximise available construction time and help offset weather-related disruptions experienced during recent weeks.

    What to expect:

    • Construction activities will occur on Sundays during the notified work hours.

    • Access to properties on Kalperri Road will be maintained.

    • Some noise associated with construction activities can be expected.

    • Existing speed restrictions will remain in place for the safety of road users and construction personnel.

  • Works commencing – Kalperri Road to Kalbeeba Road

    Share Works commencing – Kalperri Road to Kalbeeba Road on Facebook Share Works commencing – Kalperri Road to Kalbeeba Road on X (formerly Twitter) Share Works commencing – Kalperri Road to Kalbeeba Road on Linkedin Email Works commencing – Kalperri Road to Kalbeeba Road link

    When: 7 April to December 2026

    Where: Between Kalperri Road and Kalbeeba Road, Sandy Creek

    Hours of work: Monday to Saturday, 7.00am – 5.00pm (with some night works as required)

    Key details:

    • crews will be installing a new 1.2km water main alongside the existing network to increase capacity and reliability
    • works will take place on private land between Kalperri Road and Kalbeeba Road
    • construction activities will include excavators, cranes and truck movements to and from site
    • arborist works are scheduled for mid-April to support pipe installation
    • you may notice noise, dust and general construction activity during these works
    • speed restrictions will remain in place on Kalperri Road, with any traffic changes communicated in advance
    • access to properties will be maintained, and advance notice will be provided if water supply is temporarily impacted.

    These works form part of SA Water’s broader infrastructure upgrades to support growth and maintain reliable services across the region.

    We appreciate your patience while we complete these important works.

    When: 7 April to December 2026

    Where: Between Kalperri Road and Kalbeeba Road, Sandy Creek

    Hours of work: Monday to Saturday, 7.00am – 5.00pm (with some night works as required)

    Key details:

    • crews will be installing a new 1.2km water main alongside the existing network to increase capacity and reliability
    • works will take place on private land between Kalperri Road and Kalbeeba Road
    • construction activities will include excavators, cranes and truck movements to and from site
    • arborist works are scheduled for mid-April to support pipe installation
    • you may notice noise, dust and general construction activity during these works
    • speed restrictions will remain in place on Kalperri Road, with any traffic changes communicated in advance
    • access to properties will be maintained, and advance notice will be provided if water supply is temporarily impacted.

    These works form part of SA Water’s broader infrastructure upgrades to support growth and maintain reliable services across the region.

    We appreciate your patience while we complete these important works.

  • Stay informed and have your say

    Share Stay informed and have your say on Facebook Share Stay informed and have your say on X (formerly Twitter) Share Stay informed and have your say on Linkedin Email Stay informed and have your say link

    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.


    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.


  • Project Commencement

    Share Project Commencement on Facebook Share Project Commencement on X (formerly Twitter) Share Project Commencement on Linkedin Email Project Commencement link

    When: Late March 2025 until 2026

    Hours of work: 7:00 am – 5:00 pm, Monday to Friday with some weekends as required

    Key details:

    • earthwork starting in late March followed by the construction of tanks and instillation of pipes
    • during works, traffic management may be in place adjacent to the work locations
    • local access will be maintained
    • expect some noise, dust and vibration
    • We will manage works to minimise disturbances as much as possible.

    Read more about how we restore any roads, footpaths or the environment impacted by our works.

    When: Late March 2025 until 2026

    Hours of work: 7:00 am – 5:00 pm, Monday to Friday with some weekends as required

    Key details:

    • earthwork starting in late March followed by the construction of tanks and instillation of pipes
    • during works, traffic management may be in place adjacent to the work locations
    • local access will be maintained
    • expect some noise, dust and vibration
    • We will manage works to minimise disturbances as much as possible.

    Read more about how we restore any roads, footpaths or the environment impacted by our works.

Page last updated: 30 Jun 2026, 02:51 PM