Sandy Creek tanks: Kalperri Road
Water infrastructure works at Sandy Creek
Construction is now underway on two new 10 million litre above-ground water storage tanks, a new control valve building, and an underground trunk main connecting the tanks to the existing Barossa Trunk Main.
These upgrades will enhance network resilience, improve operability, and ensure reliable water services for current and future customers in the area.
For details about electrical connection to the tanks site, visit SA Power Networks.
Where we’re working
(See map below for details)
- The storage tanks are being built on secured land on the eastern side of Kalperri Road, approximately halfway between the Barossa Valley Highway and Balmoral Road in Sandy Creek.
- Water mains pipes are being installed from the tank site to the railway line near Barossa Valley Way within the land east of Kalperri Road. Pipes will then cross under Kalperri Road and continue on private land through to Kalbeeba Road.
- Pipes are also being laid from the southern side of the tanks along the paddock boundary, continuing north to the end of Warner Court.

What to expect
- Changed traffic arrangements will be in place across the area until 2026
- You may notice some noise, vibration and dust during construction
- We’ll continue working closely with the community to minimise impacts wherever possible
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Find out more about reinstatement
Nearby Works
As part of this major upgrade, other nearby works are also happening on:
Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads
Gawler East: Martin Road, Concordia Road and Sunnydale Avenue
Need more information?
Visit our FAQs page for answers to the most asked questions.
Water infrastructure works at Sandy Creek
Construction is now underway on two new 10 million litre above-ground water storage tanks, a new control valve building, and an underground trunk main connecting the tanks to the existing Barossa Trunk Main.
These upgrades will enhance network resilience, improve operability, and ensure reliable water services for current and future customers in the area.
For details about electrical connection to the tanks site, visit SA Power Networks.
Where we’re working
(See map below for details)
- The storage tanks are being built on secured land on the eastern side of Kalperri Road, approximately halfway between the Barossa Valley Highway and Balmoral Road in Sandy Creek.
- Water mains pipes are being installed from the tank site to the railway line near Barossa Valley Way within the land east of Kalperri Road. Pipes will then cross under Kalperri Road and continue on private land through to Kalbeeba Road.
- Pipes are also being laid from the southern side of the tanks along the paddock boundary, continuing north to the end of Warner Court.

What to expect
- Changed traffic arrangements will be in place across the area until 2026
- You may notice some noise, vibration and dust during construction
- We’ll continue working closely with the community to minimise impacts wherever possible
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Find out more about reinstatement
Nearby Works
As part of this major upgrade, other nearby works are also happening on:
Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads
Gawler East: Martin Road, Concordia Road and Sunnydale Avenue
Need more information?
Visit our FAQs page for answers to the most asked questions.
-
Temporary Road Closure – Kalperri Road
Share Temporary Road Closure – Kalperri Road on Facebook Share Temporary Road Closure – Kalperri Road on X (formerly Twitter) Share Temporary Road Closure – Kalperri Road on Linkedin Email Temporary Road Closure – Kalperri Road linkTo facilitate the installation of a scour valve chamber, which will support the ongoing maintenance of the water network, Kalperri Road will be temporarily closed from Monday 29 June to Friday 3 July.
When: Monday 29 June to Friday 3 July, 7:00 am – 5:00 pm
Where: Kalperri Road, Kalbeeba
Key details:
- Kalperri Road will be closed next to the rail line from 7:00 am to 5:00 pm each day.
- Local traffic will be maintained via Balmoral Road.
- Traffic will be detoured via Kalbeeba Road and Williamstown Road. Please follow signage onsite.
- We anticipate this will be the longest road closure required as part of these works. There may be one or two additional single-day closures over the coming month to complete the remaining activities.
- We apologise for the inconvenience and thank you for your patience while these essential works are completed.
To facilitate the installation of a scour valve chamber, which will support the ongoing maintenance of the water network, Kalperri Road will be temporarily closed from Monday 29 June to Friday 3 July.
When: Monday 29 June to Friday 3 July, 7:00 am – 5:00 pm
Where: Kalperri Road, Kalbeeba
Key details:
- Kalperri Road will be closed next to the rail line from 7:00 am to 5:00 pm each day.
- Local traffic will be maintained via Balmoral Road.
- Traffic will be detoured via Kalbeeba Road and Williamstown Road. Please follow signage onsite.
- We anticipate this will be the longest road closure required as part of these works. There may be one or two additional single-day closures over the coming month to complete the remaining activities.
- We apologise for the inconvenience and thank you for your patience while these essential works are completed.
-
Preparing to turn on tanks - various works
Share Preparing to turn on tanks - various works on Facebook Share Preparing to turn on tanks - various works on X (formerly Twitter) Share Preparing to turn on tanks - various works on Linkedin Email Preparing to turn on tanks - various works linkBetween June through to October, we will be preparing to bring new tanks and supporting infrastructure at the Sandy Creek site online and connect to the existing network.
What to expect
- water being released into the Sandy Creek natural creek bed, entering via council swales off Kalperri Road and flowing through nearby properties
- temporary fencing and equipment set up at various points around the site
- some works will occur 24/7, including overnight
- planned network outages with advance notice provided to impacted customers.
Between June through to October, we will be preparing to bring new tanks and supporting infrastructure at the Sandy Creek site online and connect to the existing network.
What to expect
- water being released into the Sandy Creek natural creek bed, entering via council swales off Kalperri Road and flowing through nearby properties
- temporary fencing and equipment set up at various points around the site
- some works will occur 24/7, including overnight
- planned network outages with advance notice provided to impacted customers.
-
Construction works update – temporary change in work hours
Share Construction works update – temporary change in work hours on Facebook Share Construction works update – temporary change in work hours on X (formerly Twitter) Share Construction works update – temporary change in work hours on Linkedin Email Construction works update – temporary change in work hours linkKalperri Road Tank Site Sandy Creek
Tank construction works will continue through to late 2026.
To maintain the project schedule, we will be working some Sundays.
What: Works will continue during standard construction hours of 6.00 am to 5.00 pm Monday to Saturday. Additional works will also be undertaken on Sundays between 7.00 am and 5.00 pm.
When: Sunday 14 June 2026 – Sunday 5th July 2026
Why: To maintain the project schedule and maximise available construction time and help offset weather-related disruptions experienced during recent weeks.
What to expect:
Construction activities will occur on Sundays during the notified work hours.
Access to properties on Kalperri Road will be maintained.
Some noise associated with construction activities can be expected.
Existing speed restrictions will remain in place for the safety of road users and construction personnel.
Kalperri Road Tank Site Sandy Creek
Tank construction works will continue through to late 2026.
To maintain the project schedule, we will be working some Sundays.
What: Works will continue during standard construction hours of 6.00 am to 5.00 pm Monday to Saturday. Additional works will also be undertaken on Sundays between 7.00 am and 5.00 pm.
When: Sunday 14 June 2026 – Sunday 5th July 2026
Why: To maintain the project schedule and maximise available construction time and help offset weather-related disruptions experienced during recent weeks.
What to expect:
Construction activities will occur on Sundays during the notified work hours.
Access to properties on Kalperri Road will be maintained.
Some noise associated with construction activities can be expected.
Existing speed restrictions will remain in place for the safety of road users and construction personnel.
-
Works commencing – Kalperri Road to Kalbeeba Road
Share Works commencing – Kalperri Road to Kalbeeba Road on Facebook Share Works commencing – Kalperri Road to Kalbeeba Road on X (formerly Twitter) Share Works commencing – Kalperri Road to Kalbeeba Road on Linkedin Email Works commencing – Kalperri Road to Kalbeeba Road linkWhen: 7 April to December 2026
Where: Between Kalperri Road and Kalbeeba Road, Sandy Creek
Hours of work: Monday to Saturday, 7.00am – 5.00pm (with some night works as required)
Key details:
- crews will be installing a new 1.2km water main alongside the existing network to increase capacity and reliability
- works will take place on private land between Kalperri Road and Kalbeeba Road
- construction activities will include excavators, cranes and truck movements to and from site
- arborist works are scheduled for mid-April to support pipe installation
- you may notice noise, dust and general construction activity during these works
- speed restrictions will remain in place on Kalperri Road, with any traffic changes communicated in advance
- access to properties will be maintained, and advance notice will be provided if water supply is temporarily impacted.
These works form part of SA Water’s broader infrastructure upgrades to support growth and maintain reliable services across the region.
We appreciate your patience while we complete these important works.
When: 7 April to December 2026
Where: Between Kalperri Road and Kalbeeba Road, Sandy Creek
Hours of work: Monday to Saturday, 7.00am – 5.00pm (with some night works as required)
Key details:
- crews will be installing a new 1.2km water main alongside the existing network to increase capacity and reliability
- works will take place on private land between Kalperri Road and Kalbeeba Road
- construction activities will include excavators, cranes and truck movements to and from site
- arborist works are scheduled for mid-April to support pipe installation
- you may notice noise, dust and general construction activity during these works
- speed restrictions will remain in place on Kalperri Road, with any traffic changes communicated in advance
- access to properties will be maintained, and advance notice will be provided if water supply is temporarily impacted.
These works form part of SA Water’s broader infrastructure upgrades to support growth and maintain reliable services across the region.
We appreciate your patience while we complete these important works.
-
Stay informed and have your say
Share Stay informed and have your say on Facebook Share Stay informed and have your say on X (formerly Twitter) Share Stay informed and have your say on Linkedin Email Stay informed and have your say linkAs we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.
Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.
As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.
Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.
-
Project Commencement
Share Project Commencement on Facebook Share Project Commencement on X (formerly Twitter) Share Project Commencement on Linkedin Email Project Commencement linkWhen: Late March 2025 until 2026
Hours of work: 7:00 am – 5:00 pm, Monday to Friday with some weekends as required
Key details:
- earthwork starting in late March followed by the construction of tanks and instillation of pipes
- during works, traffic management may be in place adjacent to the work locations
- local access will be maintained
- expect some noise, dust and vibration
- We will manage works to minimise disturbances as much as possible.
Read more about how we restore any roads, footpaths or the environment impacted by our works.
When: Late March 2025 until 2026
Hours of work: 7:00 am – 5:00 pm, Monday to Friday with some weekends as required
Key details:
- earthwork starting in late March followed by the construction of tanks and instillation of pipes
- during works, traffic management may be in place adjacent to the work locations
- local access will be maintained
- expect some noise, dust and vibration
- We will manage works to minimise disturbances as much as possible.
Read more about how we restore any roads, footpaths or the environment impacted by our works.
Follow Project
Latest community newsletter
Timeline
-
October - November 2024: initial aesthetics engagement
Sandy Creek tanks: Kalperri Road has finished this stageCommunity invited to share feedback on aesthetics of the tank site to inform site design.
-
January 2025: construction investigation
Sandy Creek tanks: Kalperri Road has finished this stageInvestigations inform the construction methodology.
-
Late March 2025: earthworks begin
Sandy Creek tanks: Kalperri Road has finished this stageWorks occur at the tank site off Kalperri Road.
-
Mid 2025 – early 2026: tank construction
Sandy Creek tanks: Kalperri Road is currently at this stageTanks built and installed on site.
-
Mid 2025 - early 2026: pipeline installation – off Kalperri Road
this is an upcoming stage for Sandy Creek tanks: Kalperri RoadWorks occur within land on the east of Kalperri Road.
-
Tank aesthetics - screening vegetation and tanks painting
this is an upcoming stage for Sandy Creek tanks: Kalperri Road -
June-September 2026
this is an upcoming stage for Sandy Creek tanks: Kalperri RoadCommissioning new tanks and water pipes. The tanks are set to be fully in-service by September 2026.
-
2026 - project completion
this is an upcoming stage for Sandy Creek tanks: Kalperri Road
Who's Listening
-
Phone 1300 981 233 Email metrogrowth@sawater.com.au -
Phone 0404 212 497 Email chanice.parker@mcdsrgjv.com.au -
Phone 1300 981 233 Email metrogrowth@sawater.com.au
Community newsletter
-
Metro Growth Community Newsletter June 2026 (1.16 MB) (pdf)
-
Metro Growth Community Newsletter April 2026 (1.11 MB) (pdf)
-
Metro Growth Community Newsletter February 2026 .pdf (2.4 MB) (pdf)
-
Metro Growth Community Newsletter December 2025.pdf (1.44 MB) (pdf)
-
Metro Growth Community Newsletter October 2025 (1.81 MB) (pdf)
-
Metro Growth Community Newsletter August 2025 .pdf (5 MB) (pdf)
-
Metro Growth Community Newsletter June 2025.pdf (2.36 MB) (pdf)
-
Metro Growth Community Newsletter May 2025 (2.01 MB) (pdf)
-
Metro Growth Community Newsletter April 2025 (2.01 MB) (pdf)
-
Metro Growth Community Newsletter March 2025.pdf (1.41 MB) (pdf)
Help with contacting us
Deaf, hearing or speech impaired customers.
Contact us through the National Relay Service and ask for SA Water on 1300 981 233.
- TTY users phone 133 677 then ask for SA Water on 1300 981 233
- Speak and Listen users phone 1300 555 727 then ask for SA Water on 1300 981 233

Calling from overseas
You can contact us on +61 8 7424 1735