Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads

Share Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads on Facebook Share Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads on Twitter Share Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads on Linkedin Email Gawler Belt: Paternoster, Kentish, Redbanks and Twartz Roads link

Upgrading our wastewater network in Reid, Willaston, Gawler Belt and Roseworthy

To support current and future customers in the region, we’re delivering a major upgrade to the local wastewater network.

Construction is now underway to install approximately 7.5 kilometres of new wastewater mains across Reid, Willaston, Gawler Belt, and Roseworthy, along with a new pump station on Davidson Road in Reid.

This new infrastructure will help provide reliable wastewater services to existing customers and support continued growth in the Roseworthy area.

Where we’re working
(See map below for details)

  • Paternoster Road
  • Kentish Road
  • Redbanks Road
  • Twartz Road

What to expect

  • Changed traffic arrangements will be in place across the area until mid-2026
  • Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Need more information?

Visit our FAQs page for answers to the most asked questions.

Go back to project home page




Upgrading our wastewater network in Reid, Willaston, Gawler Belt and Roseworthy

To support current and future customers in the region, we’re delivering a major upgrade to the local wastewater network.

Construction is now underway to install approximately 7.5 kilometres of new wastewater mains across Reid, Willaston, Gawler Belt, and Roseworthy, along with a new pump station on Davidson Road in Reid.

This new infrastructure will help provide reliable wastewater services to existing customers and support continued growth in the Roseworthy area.

Where we’re working
(See map below for details)

  • Paternoster Road
  • Kentish Road
  • Redbanks Road
  • Twartz Road

What to expect

  • Changed traffic arrangements will be in place across the area until mid-2026
  • Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Need more information?

Visit our FAQs page for answers to the most asked questions.

Go back to project home page




  • Traffic changes – Paternoster Road, Reid

    Share Traffic changes – Paternoster Road, Reid on Facebook Share Traffic changes – Paternoster Road, Reid on Twitter Share Traffic changes – Paternoster Road, Reid on Linkedin Email Traffic changes – Paternoster Road, Reid link

    When: early June 2025 – late 2025

    Where: Paternoster Road, Reid

    Hours of work: 7.00am to 5.00pm, Monday to Friday


    Key details:

    • we’ll be installing new wastewater pipes and inspection points under Paternoster Road
    • works will begin near Two Wells Road and move progressively north
    • from early June, works will start under Two Wells Road and continue into the nearby reserve area
    • from late June, works will move onto Paternoster Road
    • traffic management will be in place, including lane restrictions
    • our crews will be on site during the day and automated traffic lights will operate overnight
    • local access will be maintained at all times

    Find out about detours near you

  • Traffic changes on Kentish Road, Gawler Belt

    Share Traffic changes on Kentish Road, Gawler Belt on Facebook Share Traffic changes on Kentish Road, Gawler Belt on Twitter Share Traffic changes on Kentish Road, Gawler Belt on Linkedin Email Traffic changes on Kentish Road, Gawler Belt link

    When: Monday, 23 June to mid-August 2025

    Where: Kentish Road, between Parkers Road and Redbanks Road

    Hours of work: 7.00am – 5.00pm, Monday to Friday. Works may take place on weekends to help maintain schedule and minimise disruption.

    Key details:

    • pipe installation works will take place under Kentish Road
    • works will begin near the Parkers Road intersection and progress north towards Redbanks Road
    • sections of Kentish Road will be closed to traffic, with detours in place (see detour maps below)
    • please follow the detour signage onsite
    • local access will be maintained throughout the works.


    Detour: 23 June to 30 June 2025

    Temporary road closure on Kentish Road between Parkers Road and Barkley Drive

    Detour: 7 July to 20 July 2025

    Temporary road closure on Kentish Road between Barkley Drive and just north of Xavier College entrance

    Detour: 21 July to early August 2025

    Temporary road closure on Kentish Road between just north of Xavier College and Kerr Road

    Detour: late-July to mid-August between 9.00am and 2:45pm

    Temporary road closure on Kentish Rd between Kerr Road and Redbanks Rd

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    We appreciate your patience as we complete this important work.

    Read more about how we restore any roads, footpaths or the environment impacted by our works.

    Find out about detours near you

  • Stay informed and have your say

    Share Stay informed and have your say on Facebook Share Stay informed and have your say on Twitter Share Stay informed and have your say on Linkedin Email Stay informed and have your say link

    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.

Page last updated: 25 Jul 2025, 11:46 AM