Traffic changes on Kentish Road, Gawler Belt
When: 23 June to late-September 2025
Where: Kentish Road, between Parkers Road and Redbanks Road
Hours of work: 7.00am – 5.00pm, Monday to Friday. Works may take place on weekends to help maintain schedule and minimise disruption.
Key details:
- pipe installation works will take place under Kentish Road
- works will begin near the Parkers Road intersection and progress north towards Redbanks Road
- sections of Kentish Road will be closed to traffic, with detours in place (see detour maps below)
- please follow the detour signage onsite
- local access will be maintained throughout the works.
Detour 1: 21 July to late- August 2025
Temporary road closure on Kentish Road between just north of Xavier College and Kerr Road
Detour 2: Late August to late September
Temporary road closure on Kentish Rd between Kerr Road and Redbanks Rd
Traffic control will be in place at the Clancy and Redbanks intersection, to manage school traffic while this work is being completed.
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
Read more about how we restore any roads, footpaths or the environment impacted by our works.