Blakeview to Munno Para West: Craigmore Road, Curtis Road

Share Blakeview to Munno Para West: Craigmore Road, Curtis Road on Facebook Share Blakeview to Munno Para West: Craigmore Road, Curtis Road on Twitter Share Blakeview to Munno Para West: Craigmore Road, Curtis Road on Linkedin Email Blakeview to Munno Para West: Craigmore Road, Curtis Road link

From March 2025, construction works will commence to install approximately 4.4 kilometres of new water mains along Craigmore Road and Curtis Road to secure reliable services to existing customers as well as new and future customers in Angle Vale.

Works will occur from the intersection of Bentley Road and Craigmore Road through to near Leicester Grove.

The wastewater main will also be installed on Curtis Road between Andrews Road and President Avenue.

We are currently undertaking investigation works to help finalise our design and program schedule. We will update the community on our work dates as we progress.

What to expect

We’re committed to minimising disruptions and keeping you informed throughout the works.

If you’re affected by the works, we’ll let you know in advance and work closely with property owners, residents, businesses, and road users before and during the project. To complete this work as quickly as possible while keeping disruptions low, some activity may happen during the day, night, or weekends. We’re also looking at all options to reduce road closures, detours, and traffic delays.

Please note, timeline dates are subject to change based on program requirements and weather conditions.

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Go back to the project home page

From March 2025, construction works will commence to install approximately 4.4 kilometres of new water mains along Craigmore Road and Curtis Road to secure reliable services to existing customers as well as new and future customers in Angle Vale.

Works will occur from the intersection of Bentley Road and Craigmore Road through to near Leicester Grove.

The wastewater main will also be installed on Curtis Road between Andrews Road and President Avenue.

We are currently undertaking investigation works to help finalise our design and program schedule. We will update the community on our work dates as we progress.

What to expect

We’re committed to minimising disruptions and keeping you informed throughout the works.

If you’re affected by the works, we’ll let you know in advance and work closely with property owners, residents, businesses, and road users before and during the project. To complete this work as quickly as possible while keeping disruptions low, some activity may happen during the day, night, or weekends. We’re also looking at all options to reduce road closures, detours, and traffic delays.

Please note, timeline dates are subject to change based on program requirements and weather conditions.

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Go back to the project home page

  • Night works and traffic changes on Craigmore Road, Blakeview

    Share Night works and traffic changes on Craigmore Road, Blakeview on Facebook Share Night works and traffic changes on Craigmore Road, Blakeview on Twitter Share Night works and traffic changes on Craigmore Road, Blakeview on Linkedin Email Night works and traffic changes on Craigmore Road, Blakeview link

    Upcoming night works and traffic changes on Craigmore Road, Blakeview

    Our water main infrastructure works continue as part of a major network upgrade. Together with our contractors, Leed Engineering we will be undertaking nightworks to install new water mains on Craigmore Road, between Bentley Road and Main North Road.

    When: Sunday 13 April to mid-May 2025 for approximately 4 weeks

    Where: Craigmore Road, between Bentley Road and Main North Road

    Hours of work: Day works Monday to Friday, 7:00 am – 5:00 pm - Night works Sunday to Thursday 7:00 pm – 6:00 am


    Key details for full road closure

    Craigmore Road (between Bentley Road and Village Terrace) – full road closure (see map 1):

    Day and nightworks from 7.00 pm, 13 April – 5.00 pm, 17 April 2025.

    Craigmore Road (between Main Terrace and Park Lake Boulevard intersection and Main North Road intersection) – full road closure (see map 2 ):

    Day and nightworks from 7.00 pm on 27 April – 5.00 pm in mid-May 2025.


    Weekend and public holiday access

    Craigmore Road will be open to two-way traffic on weekends: Fridays 5.00 pm – Sundays 7.00 pm.

    Craigmore Road open to two-way traffic – no road works in place: 5.00 pm, 17 April – 7.00 pm, 27 April 2025.

    Detours: please follow on-site signage.

    Please note, timeline dates are subject to change based on program requirements and weather conditions.

    Thank you for your patience while these essential works are carried out.

    Go back to the list of all detours

  • Community survey

    Share Community survey on Facebook Share Community survey on Twitter Share Community survey on Linkedin Email Community survey link

    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

  • Community newsletter

    Share Community newsletter on Facebook Share Community newsletter on Twitter Share Community newsletter on Linkedin Email Community newsletter link

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.

  • Night works and traffic changes on Craigmore Road, Blakeview

    Share Night works and traffic changes on Craigmore Road, Blakeview on Facebook Share Night works and traffic changes on Craigmore Road, Blakeview on Twitter Share Night works and traffic changes on Craigmore Road, Blakeview on Linkedin Email Night works and traffic changes on Craigmore Road, Blakeview link

    Upcoming night works and traffic changes on Craigmore Road, Blakeview

    Together with our contractors, Leed Engineering we will be undertaking works to install new water mains on Craigmore Road, between Bentley Road and Park Lake Boulevard.

    When: From Sunday 23 March 2025 for approximately 3 weeks

    Where: Craigmore Road, between Bentley Road and Park Lake Boulevard


    Key details:

    Lane and road closures

    • Eastbound lane closure (Bentley Road to Park Lake Boulevard):

    5:00 am, 24 March – 5:00 pm 4 April 2025 (day closures only)


    • Full road closure

    Night closures: 7:00 pm, 23 March – 6:00 am, mid-April 2025 (Sunday to Thursday nights)

    Full closure: 7.00 pm, 7 April – mid-April 2025


    Weekend access

    Craigmore Road will be open to two-way traffic on weekends:

    Fridays 5:00 pm – Sundays 7.00 pm

    Detours: please follow on-site signage

    Hours of work:

    Day works Monday to Friday, 7:00 am – 5:00 pm
    Night works Sunday to Thursday 7:00 pm – 6:00 am

    Please note, timeline dates are subject to change based on program requirements and weather conditions.

    Thank you for your patience while these essential works are carried out.

    Go back to the list of all detours

Page last updated: 17 Apr 2025, 09:56 AM