Share Elizabeth North and Davoren Park: Midway Road to Woodford Road to Whiteparish Road to Petherton Road on Facebook Share Elizabeth North and Davoren Park: Midway Road to Woodford Road to Whiteparish Road to Petherton Road on Twitter Share Elizabeth North and Davoren Park: Midway Road to Woodford Road to Whiteparish Road to Petherton Road on Linkedin Email Elizabeth North and Davoren Park: Midway Road to Woodford Road to Whiteparish Road to Petherton Road link

Upgrading our water network in Elizabeth North and Davoren Park

To support reliable water services for existing homes and businesses, and meet the needs of growing communities, we’re delivering an upgrade to install approximately 2,400 metres of new water mains in Elizabeth North and Davoren Park.

Work has been underway since January 2025 to lay new pipes and construct gate valve chambers along the alignment to help regulate and maintain water pressure across the network.

Where we’re working
(See map below for details)

The pipeline will be installed along sections of:

  • Petherton Road
  • Heytesbury Road
  • Meadows Lane
  • Gerald Boulevard
  • under the Gawler Rail Corridor to Donnington Road
  • Old Sarum Road
  • Whiteparish Road
  • Woodford Road
  • across Main North Road to the intersection of Midway Road and McKenzie Road.

What to expect

  • Changed traffic arrangements will be in place throughout the area until the end of 2025
  • Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible
  • If you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.

Please note: Timeline dates are subject to change based on program requirements and weather conditions

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Go back to the project home page

Need more information?

Visit our FAQs page for answers to the most asked questions.

Upgrading our water network in Elizabeth North and Davoren Park

To support reliable water services for existing homes and businesses, and meet the needs of growing communities, we’re delivering an upgrade to install approximately 2,400 metres of new water mains in Elizabeth North and Davoren Park.

Work has been underway since January 2025 to lay new pipes and construct gate valve chambers along the alignment to help regulate and maintain water pressure across the network.

Where we’re working
(See map below for details)

The pipeline will be installed along sections of:

  • Petherton Road
  • Heytesbury Road
  • Meadows Lane
  • Gerald Boulevard
  • under the Gawler Rail Corridor to Donnington Road
  • Old Sarum Road
  • Whiteparish Road
  • Woodford Road
  • across Main North Road to the intersection of Midway Road and McKenzie Road.

What to expect

  • Changed traffic arrangements will be in place throughout the area until the end of 2025
  • Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible
  • If you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.

Please note: Timeline dates are subject to change based on program requirements and weather conditions

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Go back to the project home page

Need more information?

Visit our FAQs page for answers to the most asked questions.

  • Traffic changes – Whiteparish Road, Elizabeth North

    Share Traffic changes – Whiteparish Road, Elizabeth North on Facebook Share Traffic changes – Whiteparish Road, Elizabeth North on Twitter Share Traffic changes – Whiteparish Road, Elizabeth North on Linkedin Email Traffic changes – Whiteparish Road, Elizabeth North link

    When: Monday 27 October until mid-November

    Where: Whiteparish Road, Between Woodford and Charford Street

    Hours of work: 7.00 am - 6.00 pm, Monday to Friday (road closures in place 24/7)

    Key details:

    • local access to properties will be maintained
    • if your driveway is affected you will be notified in advance
    • please follow detour signage and directions on site for your safety

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    We appreciate your patience as we complete this important work.

    Find out about detours near you

    Read more about how we restore any roads, footpaths or the environment impacted by our works.

  • Traffic changes – Gerald Boulevard, Davoren Park

    Share Traffic changes – Gerald Boulevard, Davoren Park on Facebook Share Traffic changes – Gerald Boulevard, Davoren Park on Twitter Share Traffic changes – Gerald Boulevard, Davoren Park on Linkedin Email Traffic changes – Gerald Boulevard, Davoren Park link

    When: Monday 29 September until early November 2025

    Where: Gerald Boulevard, Davoren Park

    Hours of work: 7.00 am - 6.00 pm, Monday to Friday (road closures in place 24/7)

    Key details:

    • local access to properties will be maintained
    • if your driveway is affected you will be notified in advance
    • please follow detour signage via McPherson Reserve and directions on site for your safety

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    We appreciate your patience as we complete this important work.

    Find out about detours near you

    Read more about how we restore any roads, footpaths or the environment impacted by our works.

  • Stay informed and have your say

    Share Stay informed and have your say on Facebook Share Stay informed and have your say on Twitter Share Stay informed and have your say on Linkedin Email Stay informed and have your say link

    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.

Page last updated: 16 Oct 2025, 06:14 PM