Virginia: Supple Road, Angle Vale Road (from Port Wakefield Road to Robert Road)

Share Virginia: Supple Road, Angle Vale Road (from Port Wakefield Road to Robert Road) on Facebook Share Virginia: Supple Road, Angle Vale Road (from Port Wakefield Road to Robert Road) on Twitter Share Virginia: Supple Road, Angle Vale Road (from Port Wakefield Road to Robert Road) on Linkedin Email Virginia: Supple Road, Angle Vale Road (from Port Wakefield Road to Robert Road) link

Upgrading our water network in Virginia

As part of our works to upgrade infrastructure in Virginia, we’re installing around 3,000 metres of new water mains to support reliable services for existing customers as well as future customers in Riverlea.

This essential work began in September 2024 and continues along Angle Vale Road (between Robert Road and Port Wakefield Road) and Supple Road, helping to support growth in Riverlea and surrounding communities.

We’re also constructing a new pressure reducing valve on Supple Road, which will connect to the new pipe to regulate incoming water pressure from SA Water’s broader network.

Where we’re working
(See maps below for details)

Angle Vale Road (Robert Road to Supple Road)

  • Sunday to Thursday, 7:00pm to 6.00am

Supple Road

What to expect

  • Changed traffic arrangements will be in place along Angle Vale Road and Supple Road until late 2025
  • Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible
  • If you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.

Thank you for your understanding while we deliver these important upgrades to support your community.

Please note: Timeline dates are subject to change based on program requirements and weather conditions

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Go back to the project home page

Need more information?

Visit our FAQs page for answers to the most asked questions.

Upgrading our water network in Virginia

As part of our works to upgrade infrastructure in Virginia, we’re installing around 3,000 metres of new water mains to support reliable services for existing customers as well as future customers in Riverlea.

This essential work began in September 2024 and continues along Angle Vale Road (between Robert Road and Port Wakefield Road) and Supple Road, helping to support growth in Riverlea and surrounding communities.

We’re also constructing a new pressure reducing valve on Supple Road, which will connect to the new pipe to regulate incoming water pressure from SA Water’s broader network.

Where we’re working
(See maps below for details)

Angle Vale Road (Robert Road to Supple Road)

  • Sunday to Thursday, 7:00pm to 6.00am

Supple Road

What to expect

  • Changed traffic arrangements will be in place along Angle Vale Road and Supple Road until late 2025
  • Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • You may notice some noise, vibration and dust during construction
  • We’ll continue working closely with the community to minimise impacts wherever possible
  • If you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.

Thank you for your understanding while we deliver these important upgrades to support your community.

Please note: Timeline dates are subject to change based on program requirements and weather conditions

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Go back to the project home page

Need more information?

Visit our FAQs page for answers to the most asked questions.

  • Traffic changes - Angle Vale Road, between Robert Road and Supple Road

    Share Traffic changes - Angle Vale Road, between Robert Road and Supple Road on Facebook Share Traffic changes - Angle Vale Road, between Robert Road and Supple Road on Twitter Share Traffic changes - Angle Vale Road, between Robert Road and Supple Road on Linkedin Email Traffic changes - Angle Vale Road, between Robert Road and Supple Road link

    From 20 February until late March, we will commission the new water mains for Riverlea Park. Learn more about the commissioning process.

    Traffic changes will be in place on Angle Vale Road as part of these works.


    Where: Angle Vale Road, between Robert Road and Supple Road

    When: Monday 20 February to early March 2026

    Hours of work: 7.00 am to 6.00 pm

    Key details:

    • traffic changes will be in place including reduced speed and lane restrictions. Two-way traffic flow will be maintained
    • please follow signage onsite and expect some delays.
    • some water may be visible in a swale on the verge
    • local access to properties will be maintained
    • if your driveway is affected you will be notified in advance.

    Please note: Timeline dates are subject to change based on program requirements and weather conditions. In the event of extreme heat, our crews may begin work one hour earlier, commencing at 6:00am.

    We appreciate your patience as we complete this important work.

  • Stay informed and have your say

    Share Stay informed and have your say on Facebook Share Stay informed and have your say on Twitter Share Stay informed and have your say on Linkedin Email Stay informed and have your say link

    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.