Munno Para Downs to Andrews Farm: Andrews Road and Angle Vale Road
Upgrading our wastewater network on Andrews Road and Angle Vale Road
We’re upgrading wastewater infrastructure in your area to support reliable services for current and future customers in Angle Vale.
Construction is now underway, with around 10 kilometres of new wastewater mains being installed along Andrews Road and Angle Vale Road.
Where we’re working
(See map below for details)
- Along Andrews Road, from the Bellchambers Road intersection through to the Angle Vale Road intersection
- Along Angle Vale Road, from the Andrews Road intersection through to the Stebonheath Road intersection.

What to expect
- Changed traffic arrangements will be in place along Andrews Road and Angle Vale Road untilmid-2026
- Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
- You may notice some noise, vibration and dust during construction
- We’ll continue working closely with the community to minimise impacts wherever possible
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Find out more about reinstatement
Nearby Works
As part of this major upgrade, other nearby works are also happening on:
Need more information?
Visit our FAQs page for answers to the most asked questions.
Upgrading our wastewater network on Andrews Road and Angle Vale Road
We’re upgrading wastewater infrastructure in your area to support reliable services for current and future customers in Angle Vale.
Construction is now underway, with around 10 kilometres of new wastewater mains being installed along Andrews Road and Angle Vale Road.
Where we’re working
(See map below for details)
- Along Andrews Road, from the Bellchambers Road intersection through to the Angle Vale Road intersection
- Along Angle Vale Road, from the Andrews Road intersection through to the Stebonheath Road intersection.

What to expect
- Changed traffic arrangements will be in place along Andrews Road and Angle Vale Road untilmid-2026
- Work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
- You may notice some noise, vibration and dust during construction
- We’ll continue working closely with the community to minimise impacts wherever possible
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Find out more about reinstatement
Nearby Works
As part of this major upgrade, other nearby works are also happening on:
Need more information?
Visit our FAQs page for answers to the most asked questions.
-
Traffic changes - Andrews Road between Hatcher Road and Pannan Road, Munno Para Downs
Share Traffic changes - Andrews Road between Hatcher Road and Pannan Road, Munno Para Downs on Facebook Share Traffic changes - Andrews Road between Hatcher Road and Pannan Road, Munno Para Downs on Twitter Share Traffic changes - Andrews Road between Hatcher Road and Pannan Road, Munno Para Downs on Linkedin Email Traffic changes - Andrews Road between Hatcher Road and Pannan Road, Munno Para Downs linkWhen: Wednesday 3 June to Thursday 11 June 2026, (weather permitting)
Where: Andrews Road between Hatcher Road and Pannan Road
Hours of work: 7.00am to 5.00pm
Key details:
- the road will be closed for safety whilst ventilation ducts are installed on Wednesday 3 June from 9:00am to 3:00pm
- from Thursday 4 June the road will be open with a single lane closure and traffic lights from 7:00am to 5:00pm
- local resident access will be maintained under traffic control; there may be some delays
- there will be some noise, vibration and dust during these works
- please follow signage and directions from traffic controllers.
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
When: Wednesday 3 June to Thursday 11 June 2026, (weather permitting)
Where: Andrews Road between Hatcher Road and Pannan Road
Hours of work: 7.00am to 5.00pm
Key details:
- the road will be closed for safety whilst ventilation ducts are installed on Wednesday 3 June from 9:00am to 3:00pm
- from Thursday 4 June the road will be open with a single lane closure and traffic lights from 7:00am to 5:00pm
- local resident access will be maintained under traffic control; there may be some delays
- there will be some noise, vibration and dust during these works
- please follow signage and directions from traffic controllers.
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
-
Traffic changes on Andrews Road, Andrews Farm
Share Traffic changes on Andrews Road, Andrews Farm on Facebook Share Traffic changes on Andrews Road, Andrews Farm on Twitter Share Traffic changes on Andrews Road, Andrews Farm on Linkedin Email Traffic changes on Andrews Road, Andrews Farm linkWhen: 1 June to late-June
Where: Andrews Road between Petherton Road and Curtis Road
Hours of work: 7.00am - 5.00pm, Monday to Friday
Key details:
- additional crews will be working on Andrews Road and nearby streets
- to reduce the overall construction time, work will take place in multiple locations
- to safely complete the works, some sections will be closed to traffic at all times
- multiple detours will be in place for the duration of the works – please follow all onsite signage
- local and business access will be maintained at all times
- works are also continuing along Andrews Road, north of Curtis Road.
Detour map:

Please note: Timeline dates are subject to change based on program requirements and weather conditions.
When: 1 June to late-June
Where: Andrews Road between Petherton Road and Curtis Road
Hours of work: 7.00am - 5.00pm, Monday to Friday
Key details:
- additional crews will be working on Andrews Road and nearby streets
- to reduce the overall construction time, work will take place in multiple locations
- to safely complete the works, some sections will be closed to traffic at all times
- multiple detours will be in place for the duration of the works – please follow all onsite signage
- local and business access will be maintained at all times
- works are also continuing along Andrews Road, north of Curtis Road.
Detour map:

Please note: Timeline dates are subject to change based on program requirements and weather conditions.
-
Traffic changes - Andrews Road between Kernel Road and Hatcher Road, Munno Para Downs
Share Traffic changes - Andrews Road between Kernel Road and Hatcher Road, Munno Para Downs on Facebook Share Traffic changes - Andrews Road between Kernel Road and Hatcher Road, Munno Para Downs on Twitter Share Traffic changes - Andrews Road between Kernel Road and Hatcher Road, Munno Para Downs on Linkedin Email Traffic changes - Andrews Road between Kernel Road and Hatcher Road, Munno Para Downs linkWhen: Monday 1 June to Thursday 4 June, weather permitting
Where: Andrews Road between Kernel Road and Hatcher Road
Hours of work: 7.00am to 5.00pm
Key details:
- Andrews Road will be closed on Monday 1 June for safety whilst ventilation ducts are installed between 9:00am and 3:00pm
- Tuesday 2 June onward, a single lane closure with traffic lights will be in place between 7:00am and 5:00pm
- local resident access will be maintained under traffic control; there may be some delays whilst the road is made safe
- there will be some noise, vibration and dust during these works
- please follow signage and directions from traffic controllers.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
When: Monday 1 June to Thursday 4 June, weather permitting
Where: Andrews Road between Kernel Road and Hatcher Road
Hours of work: 7.00am to 5.00pm
Key details:
- Andrews Road will be closed on Monday 1 June for safety whilst ventilation ducts are installed between 9:00am and 3:00pm
- Tuesday 2 June onward, a single lane closure with traffic lights will be in place between 7:00am and 5:00pm
- local resident access will be maintained under traffic control; there may be some delays whilst the road is made safe
- there will be some noise, vibration and dust during these works
- please follow signage and directions from traffic controllers.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
-
Night works - Curtis Road, between the intersection of Andrews Road
Share Night works - Curtis Road, between the intersection of Andrews Road on Facebook Share Night works - Curtis Road, between the intersection of Andrews Road on Twitter Share Night works - Curtis Road, between the intersection of Andrews Road on Linkedin Email Night works - Curtis Road, between the intersection of Andrews Road linkWhere: Curtis Road between the intersection of Andrews Road
When: Wednesday 20 May until early June (approximately 2 weeks)
Hours of work: Monday to Thursday 7.30pm-6.00am and Sunday's – 7.00pm-6.00am
Key Details:
- Curtis Road and Andrews Road single lane closure with 3-way manual traffic lights and shuttle flow
- heavy Vehicles will be maintained under shuttle flow on Curtis Road
- outside of working hours, road will be open with road plates and speed restrictions in place.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.
Where: Curtis Road between the intersection of Andrews Road
When: Wednesday 20 May until early June (approximately 2 weeks)
Hours of work: Monday to Thursday 7.30pm-6.00am and Sunday's – 7.00pm-6.00am
Key Details:
- Curtis Road and Andrews Road single lane closure with 3-way manual traffic lights and shuttle flow
- heavy Vehicles will be maintained under shuttle flow on Curtis Road
- outside of working hours, road will be open with road plates and speed restrictions in place.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.
-
Stay informed and have your say
Share Stay informed and have your say on Facebook Share Stay informed and have your say on Twitter Share Stay informed and have your say on Linkedin Email Stay informed and have your say linkAs we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.
Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.
As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.
Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.
Follow Project
Community newsletter
-
Metro Growth Community Newsletter April 2026 (1.11 MB) (pdf)
-
Metro Growth Community Newsletter February 2026 .pdf (2.4 MB) (pdf)
-
Metro Growth Community Newsletter December 2025.pdf (1.44 MB) (pdf)
-
Metro Growth Community Newsletter October 2025 (1.81 MB) (pdf)
-
Metro Growth Community Newsletter August 2025 .pdf (5 MB) (pdf)
-
Metro Growth Community Newsletter June 2025.pdf (2.36 MB) (pdf)
-
Metro Growth Community Newsletter May 2025 (2.01 MB) (pdf)
-
Metro Growth Community Newsletter April 2025 (2.01 MB) (pdf)
-
Metro Growth Community Newsletter March 2025 (1.41 MB) (pdf)
Timeline
-
July - November 2024: construction investigation and design
Munno Para Downs to Andrews Farm: Andrews Road and Angle Vale Road has finished this stageInvestigations occur along Angle Vale Road and Andrews Road to inform the design and construction methodology.
-
May 2025: pipeline installation begins along Andrews Road and Angle Vale Road
Munno Para Downs to Andrews Farm: Andrews Road and Angle Vale Road has finished this stageWorks occur along Andrews Road from the Bellchambers Road intersection. Works occur along Angle Vale Road (between Andrews Road and the Stebonheath Road intersection). Multiple work crews will be mobilised along the alignment.
-
June 2025 until mid-2026
Munno Para Downs to Andrews Farm: Andrews Road and Angle Vale Road is currently at this stageMajor construction works are expected to continue in various sections along Andrews Road, north and south of Curtis Road until early 2026.
-
Early 2026 to mid-2026
this is an upcoming stage for Munno Para Downs to Andrews Farm: Andrews Road and Angle Vale RoadMajor construction works are expected to be near completion.
-
Mid 2026 until end 2026: expected project completion
this is an upcoming stage for Munno Para Downs to Andrews Farm: Andrews Road and Angle Vale RoadAsset commissioning and live sewer transitioning, with the new pipe set to be fully in-service by December 2026.
Who's Listening
-
Phone 1300 981 233 Email metrogrowth@sawater.com.au -
Phone 1300 981 233 Email metrogrowth@sawater.com.au -
N
Phone 1300 981 233 Email metrogrowth@sawater.com.au
Help with contacting us
Deaf, hearing or speech impaired customers.
Contact us through the National Relay Service and ask for SA Water on 1300 981 233.
- TTY users phone 133 677 then ask for SA Water on 1300 981 233
- Speak and Listen users phone 1300 555 727 then ask for SA Water on 1300 981 233

Calling from overseas
You can contact us on +61 8 7424 1735