Edinburgh North: Bellchambers and Stebonheath Road roundabout
From April 2025, construction works will commence to install approximately 86 metres of new wastewater mains and three new inspection points on the north-eastern corner of the Bellchambers and Stebonheath Road roundabout. This upgrade will ensure secure reliable services for existing customers, as well as new and future customers in the area
These works will occur concurrently with other nearby Metro Growth wastewater projects. Project teams are closely collaborating to plan detours and traffic management activities.
What to expect
We’re committed to minimising disruptions and keeping you informed throughout the works.
If you’re affected by the works, we’ll let you know in advance and work closely with property owners, residents, businesses, and road users before and during the project. To complete this work as quickly as possible while keeping disruptions low, some activity may happen during the day, night, or weekends. We’re also looking at all options to reduce road closures, detours, and traffic delays.
Please note, timeline dates are subject to change based on program requirements and weather conditions.
Nearby Works
As part of this major upgrade, other nearby works are also happening on:
- Blakeview to Munno Para West: Craigmore Road, Curtis Road
- Virginia: Supple Road, Angle Vale Road (from Port Wakefield Road to Robert Road)
- Elizabeth North and Davoren Park: Midway Road to Woodford Road to Whiteparish Road to Petherton Road
- Munno Para Downs to Andrews Farm: Andrews Road, Angle Vale Road and Curtis Road