Huntfield Heights to Noarlunga Downs: Brodie Road, River Road
Share Huntfield Heights to Noarlunga Downs: Brodie Road, River Road on FacebookShare Huntfield Heights to Noarlunga Downs: Brodie Road, River Road on TwitterShare Huntfield Heights to Noarlunga Downs: Brodie Road, River Road on LinkedinEmail Huntfield Heights to Noarlunga Downs: Brodie Road, River Road link
Upgrading our wastewater network in Onkaparinga Heights
We’re upgrading wastewater infrastructure in Noarlunga Downs, Huntfield Heights and Onkaparinga Heights to support reliable services for current and future customers.
In May 2025, installation will begin on a new gravity‑fed wastewater main. The alignment includes three sections, each crossing Main South Road via micro‑tunnelling.
This infrastructure will service and enable development of approximately 3,000 new residential allotments in Onkaparinga Heights.
Completion is expected by Mid 2027, providing increased network capacity to support future development.
Where we’re working (See map below for details)
River Road, Noarlunga Downs
Patapinda Road, Onkaparinga Heights
Adel Circuit, Huntfield Heights
Brodie Road, Huntfield Heights
What to expect
changed traffic arrangements willbe in place throughout the area until late-2026
work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
you may notice some noise, vibration and dust during construction
we’ll continue working closely with the community to minimise impacts wherever possible
If you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Upgrading our wastewater network in Onkaparinga Heights
We’re upgrading wastewater infrastructure in Noarlunga Downs, Huntfield Heights and Onkaparinga Heights to support reliable services for current and future customers.
In May 2025, installation will begin on a new gravity‑fed wastewater main. The alignment includes three sections, each crossing Main South Road via micro‑tunnelling.
This infrastructure will service and enable development of approximately 3,000 new residential allotments in Onkaparinga Heights.
Completion is expected by Mid 2027, providing increased network capacity to support future development.
Where we’re working (See map below for details)
River Road, Noarlunga Downs
Patapinda Road, Onkaparinga Heights
Adel Circuit, Huntfield Heights
Brodie Road, Huntfield Heights
What to expect
changed traffic arrangements willbe in place throughout the area until late-2026
work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
you may notice some noise, vibration and dust during construction
we’ll continue working closely with the community to minimise impacts wherever possible
If you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
What happens to roads and footpaths after our works?
We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.
Share Day and night works- Main South Road, between River Road and Melsetter Road. on FacebookShare Day and night works- Main South Road, between River Road and Melsetter Road. on TwitterShare Day and night works- Main South Road, between River Road and Melsetter Road. on LinkedinEmail Day and night works- Main South Road, between River Road and Melsetter Road. link
When:Monday 25May until early-July 2026
Where: Main South Road between River Road and Melsetter Road.
Hours of work: Day works - 7:00am-6:00pm, Monday to Friday
Night works - 7:00pm –6:00am, Sunday to Thursday nights
Key details:
at times, construction works may take place 24/7, including both day and night
changed traffic conditions may apply on Main South Road
some vibration, noise and dust are to be expected during these works.
Please note:Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
When:Monday 25May until early-July 2026
Where: Main South Road between River Road and Melsetter Road.
Hours of work: Day works - 7:00am-6:00pm, Monday to Friday
Night works - 7:00pm –6:00am, Sunday to Thursday nights
Key details:
at times, construction works may take place 24/7, including both day and night
changed traffic conditions may apply on Main South Road
some vibration, noise and dust are to be expected during these works.
Please note:Timeline dates are subject to change based on program requirements and weather conditions.
We appreciate your patience as we complete this important work.
Page last updated: 20 May 2026, 12:11 PM
Follow Project
Stay informed
Subscribe for project updates
Timeline
Early-May 2026
Huntfield Heights to Noarlunga Downs: Brodie Road, River Road has finished this stage
Site mobilisation
May 2026
Huntfield Heights to Noarlunga Downs: Brodie Road, River Road is currently at this stage
Pipeline installation commences crossing under Main South Road
Mid-2027
this is an upcoming stage for Huntfield Heights to Noarlunga Downs: Brodie Road, River Road