Salisbury Capacity Upgrade (Edinburgh Tanks)

Share Salisbury Capacity Upgrade (Edinburgh Tanks) on Facebook Share Salisbury Capacity Upgrade (Edinburgh Tanks) on X (formerly Twitter) Share Salisbury Capacity Upgrade (Edinburgh Tanks) on Linkedin Email Salisbury Capacity Upgrade (Edinburgh Tanks) link

Wastewater infrastructure works at Edinburgh

Construction is now underway on two new 15 million litre above ground storage tanks, several ancillary structures to house pumps, odour management infrastructure and process treatment units and underground pipework that connect the tanks to the existing Sailsbury Trunk Main.

These upgrades will secure high quality, reliable wastewater services for existing customers and support future housing growth in the City of Salisbury council area.

Where we’re working

(see map below for more details)

  • the storage tanks are being built on secured land on Kaurna Avenue as it is located within an existing industrial area, and the local topography helps to minimise the visual impact of the tanks on nearby residential areas
  • large diameter inlet and outlet pipework will be installed within the adjacent underground easement
  • details will be finalised once the design is completed

What to expect

  • you may notice some noise, vibration and dust during construction
  • we’ll continue working closely with the community to minimise impacts wherever possible.
Please note: Timeline dates are subject to change based on Development Application requirements, final design and weather conditions.



Wastewater infrastructure works at Edinburgh

Construction is now underway on two new 15 million litre above ground storage tanks, several ancillary structures to house pumps, odour management infrastructure and process treatment units and underground pipework that connect the tanks to the existing Sailsbury Trunk Main.

These upgrades will secure high quality, reliable wastewater services for existing customers and support future housing growth in the City of Salisbury council area.

Where we’re working

(see map below for more details)

  • the storage tanks are being built on secured land on Kaurna Avenue as it is located within an existing industrial area, and the local topography helps to minimise the visual impact of the tanks on nearby residential areas
  • large diameter inlet and outlet pipework will be installed within the adjacent underground easement
  • details will be finalised once the design is completed

What to expect

  • you may notice some noise, vibration and dust during construction
  • we’ll continue working closely with the community to minimise impacts wherever possible.
Please note: Timeline dates are subject to change based on Development Application requirements, final design and weather conditions.



  • Upcoming night and day works, Kaurna Avenue

    Share Upcoming night and day works, Kaurna Avenue on Facebook Share Upcoming night and day works, Kaurna Avenue on X (formerly Twitter) Share Upcoming night and day works, Kaurna Avenue on Linkedin Email Upcoming night and day works, Kaurna Avenue link

    When: Saturday 17 October and Saturday 7 November 2026

    Where: Kaurna Avenue, Edinburgh

    Hours of work: 2.00am to 10.00pm, each day

    Key details:

    • upcoming concrete pours requiring approximately 25 concrete trucks per hour (totalling approximately 190 per day) on each pour date
    • Kaurna Avenue northbound lane will be used as a waiting bay for concrete trucks to enter site
    • local and business access will be maintained via a 2-way lateral shift along Kaurna Avenue
    • you may notice additional noise, vibration and dust during these works.

    Detour:

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    We appreciate your patience as we complete this important work.

    When: Saturday 17 October and Saturday 7 November 2026

    Where: Kaurna Avenue, Edinburgh

    Hours of work: 2.00am to 10.00pm, each day

    Key details:

    • upcoming concrete pours requiring approximately 25 concrete trucks per hour (totalling approximately 190 per day) on each pour date
    • Kaurna Avenue northbound lane will be used as a waiting bay for concrete trucks to enter site
    • local and business access will be maintained via a 2-way lateral shift along Kaurna Avenue
    • you may notice additional noise, vibration and dust during these works.

    Detour:

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    We appreciate your patience as we complete this important work.

  • Temporary change in work hours

    Share Temporary change in work hours on Facebook Share Temporary change in work hours on X (formerly Twitter) Share Temporary change in work hours on Linkedin Email Temporary change in work hours link

    Tank construction works will continue through to late 2027, early 2028. To help maintain the project schedule, maximise available construction time and offset recent weather-related delays, some works may be undertaken on Saturdays.

    When: Saturday 20 June 2026 to late 2026

    Hours of work: 7.00 am to 5.00 pm Monday to Friday (road closures in place 24/7). Additional works may also be undertaken on Saturdays between 7.00 am and 5.00 pm


    Tank construction works will continue through to late 2027, early 2028. To help maintain the project schedule, maximise available construction time and offset recent weather-related delays, some works may be undertaken on Saturdays.

    When: Saturday 20 June 2026 to late 2026

    Hours of work: 7.00 am to 5.00 pm Monday to Friday (road closures in place 24/7). Additional works may also be undertaken on Saturdays between 7.00 am and 5.00 pm


Page last updated: 02 Oct 2026, 08:43 AM