The St Kilda Road pipe installation works have been rescheduled due to wet weather and flooding in the area.


Where: St Kilda Road, Waterloo Corner (alongside the Tramway Museum)


When:


Stage 1 - Pipeline installation: Monday, 17 August to Friday, 21 August 2026


Stage 2 - Road reinstatement and asphalting: Tuesday, 25 August 2026


Hours of work: 7:00am–5:00pm


Key details:

  • traffic will be reduced to one lane during works
  • vehicles will be able to pass through the work area under traffic controller or temporary traffic light direction
  • short delays may occur
  • increased noise, dust and mud may be experienced during construction
  • access to homes and businesses will be maintained
  • dates may change due to weather or site conditions.


Please note: Timeline dates are subject to change based on program requirements and weather conditions.

We appreciate your patience as we complete this important work.

Find out about detours near you

Share Traffic Changes: St Kilda Road rescheduled on Facebook Share Traffic Changes: St Kilda Road rescheduled on X (formerly Twitter) Share Traffic Changes: St Kilda Road rescheduled on Linkedin Email Traffic Changes: St Kilda Road rescheduled link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>