Bordertown Growth

Share Bordertown Growth on Facebook Share Bordertown Growth on X (formerly Twitter) Share Bordertown Growth on Linkedin Email Bordertown Growth link

SA Water is constructing a new 9ML water tank in the industrial estate at Bordertown off Cannawigara Road. We will lay 3km of new pipeline to connect the new tank to the existing water supply network. This major work will ensure ongoing reliability of service by decreasing the length of water supply interruptions and will allow future growth opportunities for the town which have previously not been possible due to a lack of water supply. With increased capacity in the system, SA Water will be able to provide new water connections and allow for Tatiara Council’s 10-year projected growth plan.

The new tank will enhance the capacity and resilience of the water supply, benefiting 3000 customers in the region.

The newly constructed 9ML tank at Bordertown will be commissioned, operational and supplying water to the township in late 2027. Ancillary works on the project including connections to the existing elevated tank will then continue with final project completion scheduled for mid 2028.

Please see the timeline for more information on individual components of the construction timeframe.

Traffic changes- McLellan Road and Cannawigara Road

When: 6 July to mid-July 2026

Where: McLellan Road and Cannawigara Road

Hours of work: 7.00 am to 5.00pm

Key Details:

  • detours will be in place, please follow signage onsite
  • changed traffic conditions will apply
  • some vibration, noise and dust are to be expected during these works.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

Thank you for your patience while we complete these essential works.


SA Water is constructing a new 9ML water tank in the industrial estate at Bordertown off Cannawigara Road. We will lay 3km of new pipeline to connect the new tank to the existing water supply network. This major work will ensure ongoing reliability of service by decreasing the length of water supply interruptions and will allow future growth opportunities for the town which have previously not been possible due to a lack of water supply. With increased capacity in the system, SA Water will be able to provide new water connections and allow for Tatiara Council’s 10-year projected growth plan.

The new tank will enhance the capacity and resilience of the water supply, benefiting 3000 customers in the region.

The newly constructed 9ML tank at Bordertown will be commissioned, operational and supplying water to the township in late 2027. Ancillary works on the project including connections to the existing elevated tank will then continue with final project completion scheduled for mid 2028.

Please see the timeline for more information on individual components of the construction timeframe.

Traffic changes- McLellan Road and Cannawigara Road

When: 6 July to mid-July 2026

Where: McLellan Road and Cannawigara Road

Hours of work: 7.00 am to 5.00pm

Key Details:

  • detours will be in place, please follow signage onsite
  • changed traffic conditions will apply
  • some vibration, noise and dust are to be expected during these works.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

Thank you for your patience while we complete these essential works.

  • Traffic changes- McLellan Road and Cannawigara Road

    Share Traffic changes- McLellan Road and Cannawigara Road on Facebook Share Traffic changes- McLellan Road and Cannawigara Road on X (formerly Twitter) Share Traffic changes- McLellan Road and Cannawigara Road on Linkedin Email Traffic changes- McLellan Road and Cannawigara Road link

    When: 6 July to mid-July 2026

    Where: McLellan Road and Cannawigara Road

    Hours of work: 7.00 am to 5.00pm

    Key Details:

    • detours will be in place, please follow signage onsite
    • changed traffic conditions will apply
    • some vibration, noise and dust are to be expected during these works.

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    Thank you for your patience while we complete these essential works.

    When: 6 July to mid-July 2026

    Where: McLellan Road and Cannawigara Road

    Hours of work: 7.00 am to 5.00pm

    Key Details:

    • detours will be in place, please follow signage onsite
    • changed traffic conditions will apply
    • some vibration, noise and dust are to be expected during these works.

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    Thank you for your patience while we complete these essential works.