SA Water is constructing a new 9ML water tank in the industrial estate at Bordertown off Cannawigara Road. We will lay 3km of new pipeline to connect the new tank to the existing water supply network. This major work will ensure ongoing reliability of service by decreasing the length of water supply interruptions and will allow future growth opportunities for the town which have previously not been possible due to a lack of water supply. With increased capacity in the system, SA Water will be able to provide new water connections and allow for Tatiara Council’s 10-year projected growth plan.
The new tank will enhance the capacity and resilience of the water supply, benefiting 3000 customers in the region.
The newly constructed 9ML tank at Bordertown will be commissioned, operational and supplying water to the township in late 2027. Ancillary works on the project including connections to the existing elevated tank will then continue with final project completion scheduled for mid 2028.
Please see the timeline for more information on individual components of the construction timeframe.
Traffic changes- McLellan Road and Cannawigara Road
When: 6 July to mid-July 2026
Where: McLellan Road and Cannawigara Road
Hours of work: 7.00 am to 5.00pm
Key Details:
detours will be in place, please follow signage onsite
changed traffic conditions will apply
some vibration, noise and dust are to be expected during these works.
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
Thank you for your patience while we complete these essential works.
SA Water is constructing a new 9ML water tank in the industrial estate at Bordertown off Cannawigara Road. We will lay 3km of new pipeline to connect the new tank to the existing water supply network. This major work will ensure ongoing reliability of service by decreasing the length of water supply interruptions and will allow future growth opportunities for the town which have previously not been possible due to a lack of water supply. With increased capacity in the system, SA Water will be able to provide new water connections and allow for Tatiara Council’s 10-year projected growth plan.
The new tank will enhance the capacity and resilience of the water supply, benefiting 3000 customers in the region.
The newly constructed 9ML tank at Bordertown will be commissioned, operational and supplying water to the township in late 2027. Ancillary works on the project including connections to the existing elevated tank will then continue with final project completion scheduled for mid 2028.
Please see the timeline for more information on individual components of the construction timeframe.
Traffic changes- McLellan Road and Cannawigara Road
When: 6 July to mid-July 2026
Where: McLellan Road and Cannawigara Road
Hours of work: 7.00 am to 5.00pm
Key Details:
detours will be in place, please follow signage onsite
changed traffic conditions will apply
some vibration, noise and dust are to be expected during these works.
Please note: Timeline dates are subject to change based on program requirements and weather conditions.
Thank you for your patience while we complete these essential works.
Investigations to identify any risks and inform construction methodology and design.
Ongoing: community engagement
Bordertown Growth has finished this stage
Engagement with the local community has commenced to inform residents about the upcoming works. Ongoing updates will be provided throughout the project to minimise disruption.
May 2026 – Construction Commencement
Bordertown Growth has finished this stage
Our works will commence with establishing our site compound in the industrial estate on Cannawigara Road. We will then start constructing the new 9ML water tank.
July 2026 - December 2026
Bordertown Growth is currently at this stage
In this stage of works we will lay 3.0km of new pipeline from Tatiara Tce to Cannawigara Rd to connect the new tank to the existing water supply network. Traffic management and detours will apply when we are constructing the pipeline which will only be in operation during construction, not outside of hours.
Winter 2028 - New tank commissioned
this is an upcoming stage for Bordertown Growth
Once construction and reinstatement are complete, the new 9ML water tank will be officially commissioned and fully integrated into the Bordertown's water supply network, enhancing capacity, reliability, and supporting future growth for the community.