Angle Vale to Munno Para West: Curtis Road, Heaslip Road

Share Angle Vale to Munno Para West: Curtis Road, Heaslip Road on Facebook Share Angle Vale to Munno Para West: Curtis Road, Heaslip Road on Twitter Share Angle Vale to Munno Para West: Curtis Road, Heaslip Road on Linkedin Email Angle Vale to Munno Para West: Curtis Road, Heaslip Road link

Upgrading our water and wastewater network on Curtis Road, Heaslip Road and surrounds

We’re investing in water and wastewater infrastructure along Curtis Road and Heaslip Road as part of a major network upgrade.

Curtis Road works include installing 2200 metres of wastewater mains between Andrews Road and Heaslip Road. Works are also happening on Curtis Road between Andrews Road and Stebonheath Road.

Heaslip Road works include installing 600 metres of new water and, 2200 metres of new wastewater mains from Curtis Rd moving progressively north.

This essential work is scheduled to begin in mid-march 2026 and to be completed by mid-2027.

This upgrade is an important part of strengthening the network and supporting growth in the area.

Where we’re working

Pipe installation works will take place along or across the following locations:

  • Heaslip Road and surrounding streets
  • Curtis Road (Angle Vale)
  • Across Northern Expressway
  • Curtis Road (Munno Para West)



What to expect

  • changed traffic arrangements will be in place along Curtis Road, Heaslip Road and surrounding streets until mid-2027
  • work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • you may notice some noise, vibration, and dust during construction
  • we will continue to work closely with the community to minimise impacts wherever possible
  • if you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Go back to the project home page

Need more information?

Visit our FAQs page for answers to the most asked questions.

Upgrading our water and wastewater network on Curtis Road, Heaslip Road and surrounds

We’re investing in water and wastewater infrastructure along Curtis Road and Heaslip Road as part of a major network upgrade.

Curtis Road works include installing 2200 metres of wastewater mains between Andrews Road and Heaslip Road. Works are also happening on Curtis Road between Andrews Road and Stebonheath Road.

Heaslip Road works include installing 600 metres of new water and, 2200 metres of new wastewater mains from Curtis Rd moving progressively north.

This essential work is scheduled to begin in mid-march 2026 and to be completed by mid-2027.

This upgrade is an important part of strengthening the network and supporting growth in the area.

Where we’re working

Pipe installation works will take place along or across the following locations:

  • Heaslip Road and surrounding streets
  • Curtis Road (Angle Vale)
  • Across Northern Expressway
  • Curtis Road (Munno Para West)



What to expect

  • changed traffic arrangements will be in place along Curtis Road, Heaslip Road and surrounding streets until mid-2027
  • work may take place during the day, at night or on weekends to help maintain schedule and minimise disruption
  • you may notice some noise, vibration, and dust during construction
  • we will continue to work closely with the community to minimise impacts wherever possible
  • if you're directly affected, we’ll provide advance notice and work closely with residents, businesses, and road users before and during construction.

Please note: Timeline dates are subject to change based on program requirements and weather conditions.

What happens to roads and footpaths after our works?

We work closely with the local council and follow all required reinstatement obligations, reinstating the parts of the road, footpath or the environment directly impacted by our works.

Find out more about reinstatement

Nearby Works
As part of this major upgrade, other nearby works are also happening on:

Go back to the project home page

Need more information?

Visit our FAQs page for answers to the most asked questions.

  • Traffic changes - Brookes Street, Angle Vale

    Share Traffic changes - Brookes Street, Angle Vale on Facebook Share Traffic changes - Brookes Street, Angle Vale on Twitter Share Traffic changes - Brookes Street, Angle Vale on Linkedin Email Traffic changes - Brookes Street, Angle Vale link

    We will be undertaking wastewater pipe installation on Brookes Street, Felicity Road, Macon Road, Audrey Avenue, Dijon Road and Casetta Crescent, Angle Vale. Works commenced on Brookes Street 19 May 2026 and will move progressively south.

    When: 19 May 2026 until mid-July 2026

    Where:Brookes Street (works will progress south into surrounding streets listed above)

    Hours of work: 7:00 am5:00 pm, Monday to Friday

    Key details:

    • detours will be in place, please follow signage onsite
    • changed traffic conditions will apply
    • outside of work hours, the road will be open with speed and lane restrictions
    • some vibration, noise and dust are to be expected during these works.

    Please note, traffic arrangements may change depending on site conditions. 

    We will restore any impacted roads, footpaths or the environment as soon as it’s safe and practical to do so.

    Thank you for your patience while we complete these essential works.

    Go back to the list of all detours

    We will be undertaking wastewater pipe installation on Brookes Street, Felicity Road, Macon Road, Audrey Avenue, Dijon Road and Casetta Crescent, Angle Vale. Works commenced on Brookes Street 19 May 2026 and will move progressively south.

    When: 19 May 2026 until mid-July 2026

    Where:Brookes Street (works will progress south into surrounding streets listed above)

    Hours of work: 7:00 am5:00 pm, Monday to Friday

    Key details:

    • detours will be in place, please follow signage onsite
    • changed traffic conditions will apply
    • outside of work hours, the road will be open with speed and lane restrictions
    • some vibration, noise and dust are to be expected during these works.

    Please note, traffic arrangements may change depending on site conditions. 

    We will restore any impacted roads, footpaths or the environment as soon as it’s safe and practical to do so.

    Thank you for your patience while we complete these essential works.

    Go back to the list of all detours

  • Traffic changes - Ashwin Street, Angle Vale

    Share Traffic changes - Ashwin Street, Angle Vale on Facebook Share Traffic changes - Ashwin Street, Angle Vale on Twitter Share Traffic changes - Ashwin Street, Angle Vale on Linkedin Email Traffic changes - Ashwin Street, Angle Vale link

    Works to install new wastewater pipes on Ashwin Street, commenced in early May 2026. Works will move progressively east, with additional works to be undertaken on surrounding streets.

    When: early-May until early-June 2026

    Where:Ashwin Street, Angle Vale

    Hours of work: 7:00 am5:00 pm, Monday to Friday

    Key details:

    • detours will be in place, please follow signage onsite
    • changed traffic conditions will apply
    • outside of work hours, the road will be open with speed and lane restrictions
    • some vibration, noise and dust are to be expected during these works.

    Please note, traffic arrangements may change depending on site conditions. 

    We will restore any impacted roads, footpaths or the environment as soon as it’s safe and practical to do so.

    Thank you for your patience while we complete these essential works.

    Works to install new wastewater pipes on Ashwin Street, commenced in early May 2026. Works will move progressively east, with additional works to be undertaken on surrounding streets.

    When: early-May until early-June 2026

    Where:Ashwin Street, Angle Vale

    Hours of work: 7:00 am5:00 pm, Monday to Friday

    Key details:

    • detours will be in place, please follow signage onsite
    • changed traffic conditions will apply
    • outside of work hours, the road will be open with speed and lane restrictions
    • some vibration, noise and dust are to be expected during these works.

    Please note, traffic arrangements may change depending on site conditions. 

    We will restore any impacted roads, footpaths or the environment as soon as it’s safe and practical to do so.

    Thank you for your patience while we complete these essential works.

  • Night works - Curtis Road, between the intersection of Andrews Road

    Share Night works - Curtis Road, between the intersection of Andrews Road on Facebook Share Night works - Curtis Road, between the intersection of Andrews Road on Twitter Share Night works - Curtis Road, between the intersection of Andrews Road on Linkedin Email Night works - Curtis Road, between the intersection of Andrews Road link

    Where: Curtis Road between the intersection of Andrews Road

    When: Wednesday 20 May until early June (approximately 2 weeks)

    Hours of work: Monday to Thursday 7.30pm-6.00am and Sunday's, 7.00pm-6.00am

    Key Details:

    • Curtis Road and Andrews Road single lane closure with 3-way manual traffic lights and shuttle flow
    • heavy vehicles will be maintained under shuttle flow on Curtis Road
    • outside of working hours, road will be open with road plates and speed restrictions in place.

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    Find out about detours near you

    Where: Curtis Road between the intersection of Andrews Road

    When: Wednesday 20 May until early June (approximately 2 weeks)

    Hours of work: Monday to Thursday 7.30pm-6.00am and Sunday's, 7.00pm-6.00am

    Key Details:

    • Curtis Road and Andrews Road single lane closure with 3-way manual traffic lights and shuttle flow
    • heavy vehicles will be maintained under shuttle flow on Curtis Road
    • outside of working hours, road will be open with road plates and speed restrictions in place.

    Please note: Timeline dates are subject to change based on program requirements and weather conditions.

    Find out about detours near you

  • Night works - Heaslip Road

    Share Night works - Heaslip Road on Facebook Share Night works - Heaslip Road on Twitter Share Night works - Heaslip Road on Linkedin Email Night works - Heaslip Road link

    Works to install new water and wastewater pipes on Heaslip Road, near Curtis Road, commenced in early March 2026. Works will move progressively north, with completion expected mid-2027.

    Additional works will also be undertaken on surrounding streets.

    Where: Heaslip Road, between Shiraz Avenue and Angle Vale Road, Angle Vale

    When: April until late May 2026

    Hours of work: 7:00pm – 6:00am, Sunday to Friday

    Key details:

    • HeaslipRoad will be closed to traffic between MaxFatchenDrive and Angle Vale Road atnight Sunday to Friday
    • local and business access will be maintained at all times
    • detours will be in place, please follow signage onsite
    • outside of work hours, the road will be open with speed restrictions
    • to reduce the overall construction time, work will occur in multiple locations along Heaslip Road
    • some vibration, noise and dust are to be expected during these works.

    Please note, traffic arrangements may change depending on site conditions.

    We will restore any impacted roads, footpaths or the environment as soon as it’s safe and practical to do so.

    Thank you for your patience while we complete these essential works.

    Go back to the list of all detours

    Works to install new water and wastewater pipes on Heaslip Road, near Curtis Road, commenced in early March 2026. Works will move progressively north, with completion expected mid-2027.

    Additional works will also be undertaken on surrounding streets.

    Where: Heaslip Road, between Shiraz Avenue and Angle Vale Road, Angle Vale

    When: April until late May 2026

    Hours of work: 7:00pm – 6:00am, Sunday to Friday

    Key details:

    • HeaslipRoad will be closed to traffic between MaxFatchenDrive and Angle Vale Road atnight Sunday to Friday
    • local and business access will be maintained at all times
    • detours will be in place, please follow signage onsite
    • outside of work hours, the road will be open with speed restrictions
    • to reduce the overall construction time, work will occur in multiple locations along Heaslip Road
    • some vibration, noise and dust are to be expected during these works.

    Please note, traffic arrangements may change depending on site conditions.

    We will restore any impacted roads, footpaths or the environment as soon as it’s safe and practical to do so.

    Thank you for your patience while we complete these essential works.

    Go back to the list of all detours

  • Stay informed and have your say

    Share Stay informed and have your say on Facebook Share Stay informed and have your say on Twitter Share Stay informed and have your say on Linkedin Email Stay informed and have your say link

    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.

    As we upgrade our water and wastewater networks, we’d love to hear from you. Your feedback helps us understand what’s working well and where we can improve. Visit this link to have your say.

    Read our Community Newsletter for updates on works happening near you, how we’re working to minimise disruptions, and ways to stay informed.

Page last updated: 20 May 2026, 10:46 AM