September → November 2022
Monitoring of Warren Reservoir fish population
October → November 2022
Broad stakeholder engagement
February 2023
Warren Reservoir Reserve stage one closure
March 2023
Warren Reservoir Reserve stage 2 closure and lowering of remaining water
March → April 2023
Fish relocation activities
April 2023
Complete full draining of Warren Reservoir
April → August 2023
Undertake valve upgrade works
August → September 2023
Refill Warren Reservoir
October 2023
Warren Reservoir re-opens to the public