The first 17 properties at our pilot site at Glenere Drive, Modbury were connected to our sewer network in August 2021.

Activities to connect the next 45 properties began in November 2021 at our second pilot site at Dawson Drive, Angas Court and North East Road, Modbury.

The work completed at these two pilots sites has given us the insight required to manage the complexities of the program, while delivering customer outcomes with minimum impact and maximum benefit for the community.

Installing new pipe work under brick paving at a property in Glenere Drive, Modbury

Installing a new connection to a property from the new sewer main in Dawson Drive, Modbury



The first 17 properties at our pilot site at Glenere Drive, Modbury were connected to our sewer network in August 2021.

Activities to connect the next 45 properties began in November 2021 at our second pilot site at Dawson Drive, Angas Court and North East Road, Modbury.

The work completed at these two pilots sites has given us the insight required to manage the complexities of the program, while delivering customer outcomes with minimum impact and maximum benefit for the community.

Installing new pipe work under brick paving at a property in Glenere Drive, Modbury

Installing a new connection to a property from the new sewer main in Dawson Drive, Modbury