Night works and traffic changes on Craigmore Road, Blakeview

Upcoming night works and traffic changes on Craigmore Road, Blakeview

Our water main infrastructure works continue as part of a major network upgrade. Together with our contractors, Leed Engineering we will be undertaking nightworks to install new water mains on Craigmore Road, between Bentley Road and Main North Road.

When: Sunday 13 April to mid-May 2025 for approximately 4 weeks

Where: Craigmore Road, between Bentley Road and Main North Road

Hours of work: Day works Monday to Friday, 7:00 am – 5:00 pm - Night works Sunday to Thursday 7:00 pm – 6:00 am


Key details for full road closure

Craigmore Road (between Bentley Road and Village Terrace) – full road closure (see map 1):

Day and nightworks from 7.00 pm, 13 April – 5.00 pm, 17 April 2025.

Craigmore Road (between Main Terrace and Park Lake Boulevard intersection and Main North Road intersection) – full road closure (see map 2 ):

Day and nightworks from 7.00 pm on 27 April – 5.00 pm in mid-May 2025.


Weekend and public holiday access

Craigmore Road will be open to two-way traffic on weekends: Fridays 5.00 pm – Sundays 7.00 pm.

Craigmore Road open to two-way traffic – no road works in place: 5.00 pm, 17 April – 7.00 pm, 27 April 2025.

Detours: please follow on-site signage.

Please note, timeline dates are subject to change based on program requirements and weather conditions.

Thank you for your patience while these essential works are carried out.

Go back to the list of all detours

Share Night works and traffic changes on Craigmore Road, Blakeview on Facebook Share Night works and traffic changes on Craigmore Road, Blakeview on Twitter Share Night works and traffic changes on Craigmore Road, Blakeview on Linkedin Email Night works and traffic changes on Craigmore Road, Blakeview link