Share Moana Growth (Tatachilla Road & Maslin Beach Road) on FacebookShare Moana Growth (Tatachilla Road & Maslin Beach Road) on TwitterShare Moana Growth (Tatachilla Road & Maslin Beach Road) on LinkedinEmail Moana Growth (Tatachilla Road & Maslin Beach Road) link
SA Water together with McConnell Diona Joint Venture (MDJV) are installing a new water main to support growth in the Moana area.
What we are doing and when
The project involves installing 4.2 kilometres of new water main pipework along Tatachilla Road (from California Road to Main South Road), Maslin Beach Road and the southern section of Commercial Road.
Works on Tatachilla Road commenced from Monday 3 February 2025. Works on Maslin Beach Road will begin following the completion of works on Tatachilla Road by end of March/early April 2025. These works will be carried out as day works between 7am to 5pm weekdays. Our main work zone will generally move in west and are estimated to be completed within approximately 6 weeks.
As previously communicated, while timeframes are indicative of our project timeline, times and dates may change depending on weather conditions and any technical constraints our teams may encounter.
How will this affect you?
Works will be completed in stages with sectional road closures and detours required (noting strict local access only in some locations). To minimise these impacts, traffic management (including traffic controllers) and advance notification to road users will be in place.
These works require the use of noise generating machinery, hence construction activities may result in some noise and disruption impacts to nearby residents and businesses. Though construction noise cannot be avoided, where possible MDJV will make every reasonable and practicable effort to minimise noise and disruption resulting from these works.
We will notify you in advance should any of these works require a planned and temporary disruption to your water supply, though this is not anticipated for these works.
Please see the maps over the page which show the locations of the pending works along Tatachilla Road.
Detour Maps for works along Maslin Beach Rd are also now available below for your reference
Remaining works for Tatachilla Rd will primarily be day works and will continue till late March. Note applicable detours below-
SA Water together with McConnell Diona Joint Venture (MDJV) are installing a new water main to support growth in the Moana area.
What we are doing and when
The project involves installing 4.2 kilometres of new water main pipework along Tatachilla Road (from California Road to Main South Road), Maslin Beach Road and the southern section of Commercial Road.
Works on Tatachilla Road commenced from Monday 3 February 2025. Works on Maslin Beach Road will begin following the completion of works on Tatachilla Road by end of March/early April 2025. These works will be carried out as day works between 7am to 5pm weekdays. Our main work zone will generally move in west and are estimated to be completed within approximately 6 weeks.
As previously communicated, while timeframes are indicative of our project timeline, times and dates may change depending on weather conditions and any technical constraints our teams may encounter.
How will this affect you?
Works will be completed in stages with sectional road closures and detours required (noting strict local access only in some locations). To minimise these impacts, traffic management (including traffic controllers) and advance notification to road users will be in place.
These works require the use of noise generating machinery, hence construction activities may result in some noise and disruption impacts to nearby residents and businesses. Though construction noise cannot be avoided, where possible MDJV will make every reasonable and practicable effort to minimise noise and disruption resulting from these works.
We will notify you in advance should any of these works require a planned and temporary disruption to your water supply, though this is not anticipated for these works.
Please see the maps over the page which show the locations of the pending works along Tatachilla Road.
Detour Maps for works along Maslin Beach Rd are also now available below for your reference