Ceduna Tank and Pipeline Project
Together with our contractor, McConnell Dowell Diona joint venture (MDJV), we are building a new 4.5 megalitre water storage tank and 12-kilometre underground pipeline into the Ceduna township. This project will improve water security for Ceduna now and into the future.
The new tank is being constructed next to the existing tanks located on Kalanbi Road. The new pipeline will be located on a mixture of private property and road reserve which runs between the new tank and our existing pipeline network in Ceduna.
When it’s happening
Works commenced in November 2024, and we expect them to be completed by mid-2026. The start and duration of works are dependent on weather conditions and any technical constraints we may encounter. We will endeavour to complete this project as quickly as possible, with minimal impact to the community.
Access to properties in the area will be maintained during these works.
What to expect
We will have traffic management in place around our site to ensure safety of the community and our crews. As our works move into Ceduna township, there will be temporary road closures along Schwarz Street.
Local employment opportunities
Our framework delivery partner - McConnell Dowell Diona joint venture (MDJV) - have used local employees as much as possible during these works, with local labourers, machinery operators and site administration part of the team.
Mid 2025 update
In mid-late May, our crews began installing 36 pre-cast panels for the water storage tank, with this component of work expected to be complete around mid-July 2025.
Ceduna Tank and Pipeline Project
Together with our contractor, McConnell Dowell Diona joint venture (MDJV), we are building a new 4.5 megalitre water storage tank and 12-kilometre underground pipeline into the Ceduna township. This project will improve water security for Ceduna now and into the future.
The new tank is being constructed next to the existing tanks located on Kalanbi Road. The new pipeline will be located on a mixture of private property and road reserve which runs between the new tank and our existing pipeline network in Ceduna.
When it’s happening
Works commenced in November 2024, and we expect them to be completed by mid-2026. The start and duration of works are dependent on weather conditions and any technical constraints we may encounter. We will endeavour to complete this project as quickly as possible, with minimal impact to the community.
Access to properties in the area will be maintained during these works.
What to expect
We will have traffic management in place around our site to ensure safety of the community and our crews. As our works move into Ceduna township, there will be temporary road closures along Schwarz Street.
Local employment opportunities
Our framework delivery partner - McConnell Dowell Diona joint venture (MDJV) - have used local employees as much as possible during these works, with local labourers, machinery operators and site administration part of the team.
Mid 2025 update
In mid-late May, our crews began installing 36 pre-cast panels for the water storage tank, with this component of work expected to be complete around mid-July 2025.